BLD01-00324
| BLD-Aging Inspection | 7/10/2001 | 7/10/2001 | 7/10/2001 12:00:00 AM | | PASS |
|
|
wip 7/10/2001 7:57:47 AM
|
BLD01-00161
| BLD-Aging Inspection | 7/10/2001 | 7/10/2001 | 7/10/2001 12:00:00 AM | | PASS |
|
|
wip 7/10/2001 7:58:33 AM
|
BLD01-00903
| BLD-Aging Inspection | 7/10/2001 | 7/10/2001 | 7/10/2001 12:00:00 AM | | PASS |
|
|
wip 7/10/2001 7:59:11 AM
|
BLD00-03626
| BLD-Conference | 7/10/2001 | 7/10/2001 | 7/10/2001 12:00:00 AM | | PART |
|
|
Issue CN for 30 notice. Posted CN and verbally informed owner of pending date for demolition per permit condition. 7/10/2001 2:48:41 PM
|
BLD01-01709
| BLD-Footing | 7/9/2001 | 7/10/2001 | 7/10/2001 12:00:00 AM | A | PART |
|
|
Jed ###-#### wip--Received soil compaction report from contractor 95% compaction received. 7/10/2001 10:36:38 AM
|
BLD01-00837
| BLD-Framing/Rough-in | 7/9/2001 | 7/10/2001 | 7/10/2001 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 07/09/2001 at 15:54:39. Contact: ###-####.
|
BLD01-00541
| BLD-Framing/Rough-in | 7/9/2001 | 7/10/2001 | 7/10/2001 12:00:00 AM | A | FAIL |
|
|
Rick ###-#### shear wall C/N issued-- 7/10/2001 9:12:32 AM
|
BLD01-01508
| BLD-Footing | 7/10/2001 | 7/10/2001 | 7/10/2001 12:00:00 AM | P | CANC |
|
|
Scheduled by a contractor via Hello! on 07/10/2001 at 07:55:19. Contact: ###-####. Cancelled by contractor 7/10/2001 12:54:02 PM
|
BLD01-01444
| BLD-Foundation | 7/10/2001 | 7/10/2001 | 7/10/2001 12:00:00 AM | P | PART |
|
|
CHRIS ###-#### wip 7/10/2001 12:14:42 PM
|
BLD01-00837
| BLD-Framing/Rough-in | 7/10/2001 | 7/10/2001 | 7/10/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by Inspector: 420 On 7/10/2001 9:30:48 AM ok to isulate--need r.i. approval on fireplace. 7/10/2001 1:30:53 PM
|
BLD01-01723
| BLD-Footing | 7/10/2001 | 7/10/2001 | 7/10/2001 12:00:00 AM | P | PART |
|
|
late pm \\###-#### wip 7/10/2001 2:19:14 PM
|
BLD01-01725
| BLD-Footing | 7/10/2001 | 7/10/2001 | 7/10/2001 12:00:00 AM | P | CANC |
|
|
Cancelled by contractor 7/10/2001 2:18:56 PM
|