ELE02-02065
| Rough-In Permanent Service | 7/8/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | A | PASS |
|
|
steve- ###-#### p/s ug n ok 7/10/2002 11:01:06 AM
|
ELE02-02066
| Rough-In Permanent Service | 7/8/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | A | PASS |
|
|
steve- ###-#### r/i & ser p/s ug n ok 7/10/2002 11:00:42 AM
|
ELE02-02067
| Temporary Service | 7/8/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | A | PASS |
|
|
steve ###-#### t/p t/s ug n ok 7/10/2002 10:41:20 AM
|
ELE02-02081
| Temporary Service | 7/9/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | A | CANC |
|
|
t/p- kevin- ###-####
|
ELE02-02082
| Temporary Service | 7/9/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | A | CANC |
|
|
kevin ###-#### t/p
|
ELE02-02083
| Temporary Service | 7/9/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | A | CANC |
|
|
kevin ###-####
|
ELE02-01503
| Electrical Rough-In | 7/9/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 07/09/2002 at 13:37:28. Contact: ###-####. parking lot light trench [part] 7/10/2002 10:27:45 AM
|
ELE01-04231
| Final | 7/9/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | A | PASS |
|
|
GREG ###-####
|
ELE02-01276
| Final | 7/10/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | P | PASS |
|
|
ALAN ###-####
|
ELE02-01977
| Rough-In Permanent Service | 7/10/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | P | FAIL |
|
|
###-#### as late as possible not ready 7/10/2002 5:53:06 PM
|
ELE02-02091
| Rough-In Permanent Service | 7/10/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | P | PASS |
|
|
LEE ###-#### pool bond ok 7/10/2002 2:34:38 PM
|
ELE02-01503
| Electrical Rough-In | 7/10/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 07/10/2002 at 09:08:03. Contact: ###-####. under ground to transf. ok 7/11/2002 9:56:09 AM
|
ELE02-00075
| Electrical Rough-In | 7/10/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 07/10/2002 at 09:19:26. Contact: ###-####. ceiling cover ok 7/10/2002 1:05:21 PM
|