BLD01-02017
| BLD-Final | 7/9/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | A | NR |
|
|
###-#### still needs elec final 7/10/2002 10:44:41 AM
|
BLD02-00155
| BLD-Footing | 7/9/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | A | NR |
|
|
late am ###-####
|
MEC02-01869
| Pressure Test | 7/9/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/09/2002 at 15:06:56. Contact: ###-####.
|
BLD02-00832
| BLD-Final | 7/9/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | A | PASS |
|
|
###-####. 7/9/2002 6:14:35 PM
|
BLD01-00875
| BLD-Framing/Rough-in | 7/8/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | A | CANC |
|
|
roger- -###-#### fr
|
BLD02-00554
| BLD-Foundation | 7/9/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | A | CANC |
|
|
Scheduled by a contractor via Hello! on 07/09/2002 at 08:12:51. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 07/10/2002 at 07:15:02.
|
BLD02-00757
| BLD-Framing/Rough-in | 7/9/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | A | PART |
|
|
JACK ###-#### CELING GRID pods ok crew can start dropping in pannels but need to leave out areas so elec and mec can inspect 7/10/2002 10:03:27 AM
|
BLD02-01597
| BLD-Framing/Rough-in | 7/9/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | P | CANC |
|
|
###-#### charity rebar
|
BLD02-00554
| BLD-Foundation | 7/10/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 07/10/2002 at 07:16:06. Contact: ###-####.rebar in forms about 80% complete 7/10/2002 2:52:04 PM
|
BLD02-00558
| BLD-Footing | 7/10/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 07/10/2002 at 07:17:02. Contact: ###-####. set backs ok forms at about 75 % no rebar installed 7/10/2002 2:53:03 PM
|
BLD02-01267
| BLD-Final | 7/10/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | P | PASS |
|
|
###-#### bryan
|
BLD01-02764
| BLD-Final | 7/10/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | P | PASS |
|
|
###-####c.c # 164 90 issued 7/10/2002 1:47:07 PM
|
BLD02-00155
| BLD-Footing | 7/10/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | P | PART |
|
|
mti on site this project is being covered by spec inspection nent over project with in spector 7/10/2002 2:51:26 PM
|
BLD02-01597
| BLD-Concrete | 7/10/2002 | 7/10/2002 | 7/10/2002 12:00:00 AM | P | PASS |
|
|
|