FIR05-00698 INSP-Final Inspection7/9/20097/10/20097/10/2009 5:05:49 PMAPART
Fire alarm testing completed satisfactory today includes the FACP, nac panels, remote annunciator, elevator recall functions, mag locks at exit doors, signals sent to remote station, all initiating devices and sprinkler monitoring per new plan resubmittals. Items needed for final include retest the non-functional duct detector at the roof, provide correct addressing at three smoke detectors, repair one MP and replace one h/s on the first floor, provide a map at the annunciator, show locations of hoistway sd and hd on the site map, verifiy functionality of notification appliances throughout.
FIR05-00750 INSP-Final Inspection7/9/20097/10/20097/10/2009 4:50:07 PMAPART
This permit is approved for final when shell building fire alarm permit is finaled.
FIR05-00751 INSP-Final Inspection7/9/20097/10/20097/10/2009 4:48:49 PMAPART
This permit is okay for final when shell building fire alarm permit is finaled.
FIR05-00752 INSP-Final Inspection7/9/20097/10/20097/10/2009 4:47:43 PMAPART
Initiating device testing passed, final pending notification appliance testing for one relocated 110cd strobe at the dining area per resubmitted plans.
FIR05-00753 INSP-Final Inspection7/9/20097/10/20097/10/2009 4:46:40 PMAPART
Final pending repair of one manual pull station and replace one 30cd HS at the dining area.
FIR09-00164 INSP-Sprinkler Rough-in/Hydro7/10/20097/10/20097/10/2009 4:40:36 PMPPART
Okay to cover ceilings at the north classroom wing per notations on plan, also inspected rough-in above the folding partition wall at the new gym.
BLD09-00601 FIRE-Final Inspection7/10/20097/10/20097/10/2009 4:38:02 PMPPASS
Fire life safety inspection passed.
FIR09-00033 INSP-Sprinkler Rough-in/Hydro7/10/20097/10/20097/10/2009 4:37:22 PMPPART
Overhead hydrostatic tests for systems #3 thru 11 at the dry goods warehouse passed with the exception of system #5 where visible leakage at one coupling was noted. Hydrostatic test for system #12 office area also completed acceptable.
FIR09-00054 FIR-Aging Inspection7/10/20097/10/20097/10/2009 4:33:08 PM DONE
Work in progress
FIR09-00372 INSP-Final Inspection7/7/20097/10/20097/10/2009 4:32:11 PMAPASS
Scope of fire alarm work passed field testing, permit finaled.
FIR08-00439 INSP-Final Inspection7/9/20097/10/20097/10/2009 4:29:50 PMAFAIL
Correction notice item from the previous inspection done 6/18 is not finished. Pendent head at the master closet obstructed by an adjacent light fixture.
FIR08-00438 INSP-Final Inspection7/9/20097/10/20097/10/2009 4:27:23 PMAFAIL
Two sprinkler heads will need replaced due to paint at the elements and seats-including one sw head at the bedroom, one pendent head at a mechanical closet.
FIR08-00436 INSP-Final Inspection7/9/20097/10/20097/10/2009 4:24:40 PMAPASS
Fire sprinkler permit approved for final.
FIR09-00033 INSP-Sprinkler Rough-in/Hydro7/10/20097/10/20097/10/2009 4:23:19 PMAFAIL
Hydrostatic test for systems #1 and #2 failed due to pressure loss at the guage and visible leakage at some locations.