FIR05-00698
| INSP-Final Inspection | 7/9/2009 | 7/10/2009 | 7/10/2009 5:05:49 PM | A | PART |
|
|
Fire alarm testing completed satisfactory today includes the FACP, nac panels, remote annunciator, elevator recall functions, mag locks at exit doors, signals sent to remote station, all initiating devices and sprinkler monitoring per new plan resubmittals. Items needed for final include retest the non-functional duct detector at the roof, provide correct addressing at three smoke detectors, repair one MP and replace one h/s on the first floor, provide a map at the annunciator, show locations of hoistway sd and hd on the site map, verifiy functionality of notification appliances throughout.
|
FIR05-00750
| INSP-Final Inspection | 7/9/2009 | 7/10/2009 | 7/10/2009 4:50:07 PM | A | PART |
|
|
This permit is approved for final when shell building fire alarm permit is finaled.
|
FIR05-00751
| INSP-Final Inspection | 7/9/2009 | 7/10/2009 | 7/10/2009 4:48:49 PM | A | PART |
|
|
This permit is okay for final when shell building fire alarm permit is finaled.
|
FIR05-00752
| INSP-Final Inspection | 7/9/2009 | 7/10/2009 | 7/10/2009 4:47:43 PM | A | PART |
|
|
Initiating device testing passed, final pending notification appliance testing for one relocated 110cd strobe at the dining area per resubmitted plans.
|
FIR05-00753
| INSP-Final Inspection | 7/9/2009 | 7/10/2009 | 7/10/2009 4:46:40 PM | A | PART |
|
|
Final pending repair of one manual pull station and replace one 30cd HS at the dining area.
|
FIR09-00164
| INSP-Sprinkler Rough-in/Hydro | 7/10/2009 | 7/10/2009 | 7/10/2009 4:40:36 PM | P | PART |
|
|
Okay to cover ceilings at the north classroom wing per notations on plan, also inspected rough-in above the folding partition wall at the new gym.
|
BLD09-00601
| FIRE-Final Inspection | 7/10/2009 | 7/10/2009 | 7/10/2009 4:38:02 PM | P | PASS |
|
|
Fire life safety inspection passed.
|
FIR09-00033
| INSP-Sprinkler Rough-in/Hydro | 7/10/2009 | 7/10/2009 | 7/10/2009 4:37:22 PM | P | PART |
|
|
Overhead hydrostatic tests for systems #3 thru 11 at the dry goods warehouse passed with the exception of system #5 where visible leakage at one coupling was noted. Hydrostatic test for system #12 office area also completed acceptable.
|
FIR09-00054
| FIR-Aging Inspection | 7/10/2009 | 7/10/2009 | 7/10/2009 4:33:08 PM | | DONE |
|
|
Work in progress
|
FIR09-00372
| INSP-Final Inspection | 7/7/2009 | 7/10/2009 | 7/10/2009 4:32:11 PM | A | PASS |
|
|
Scope of fire alarm work passed field testing, permit finaled.
|
FIR08-00439
| INSP-Final Inspection | 7/9/2009 | 7/10/2009 | 7/10/2009 4:29:50 PM | A | FAIL |
|
|
Correction notice item from the previous inspection done 6/18 is not finished. Pendent head at the master closet obstructed by an adjacent light fixture.
|
FIR08-00438
| INSP-Final Inspection | 7/9/2009 | 7/10/2009 | 7/10/2009 4:27:23 PM | A | FAIL |
|
|
Two sprinkler heads will need replaced due to paint at the elements and seats-including one sw head at the bedroom, one pendent head at a mechanical closet.
|
FIR08-00436
| INSP-Final Inspection | 7/9/2009 | 7/10/2009 | 7/10/2009 4:24:40 PM | A | PASS |
|
|
Fire sprinkler permit approved for final.
|
FIR09-00033
| INSP-Sprinkler Rough-in/Hydro | 7/10/2009 | 7/10/2009 | 7/10/2009 4:23:19 PM | A | FAIL |
|
|
Hydrostatic test for systems #1 and #2 failed due to pressure loss at the guage and visible leakage at some locations.
|