ESC11-00874
| General Inspection | 7/3/2012 | 7/3/2012 | | | |
|
|
|
ESC12-00593
| Site Preparation | 7/5/2012 | 7/5/2012 | | | |
|
|
|
ESC11-00253
| Aging Inspection | 7/5/2012 | 7/5/2012 | | | |
|
|
|
BLD12-01422
| BLD-Other | 7/9/2012 | 7/10/2012 | 7/11/2012 8:24:58 AM | P | PASS |
|
|
(Falcon Bldg) Ceiling grid -- Kevin Phone #: ###-####
|
MIS12-00189
| BLD-Conference | 7/10/2012 | 7/10/2012 | 7/10/2012 3:56:07 PM | P | DONE |
|
|
roofing being done with out a permit
|
MIS12-00189
| DOC - Permit Finaled | 7/10/2012 | 7/10/2012 | 7/10/2012 3:55:57 PM | P | PASS |
|
|
A stop work and double fee was issued. A roofing permit has been issued.
|
ESC12-00507
| Random Inspection | 7/10/2012 | 7/10/2012 | 7/10/2012 3:39:10 PM | P | PASS |
|
|
|
BLD12-01256
| BLD-Framing/Rough-in | 7/10/2012 | 7/10/2012 | 7/10/2012 3:38:49 PM | P | FAIL |
|
|
kelly Phone #: ###-####. Remove all insulation for framing inspection.
|
BLD12-01256
| BLD-Energy code compliance | 7/10/2012 | 7/10/2012 | 7/10/2012 3:38:10 PM | P | FAIL |
|
|
kelly Phone #: ###-####
|
BLD12-00524
| BLD-Other | 7/10/2012 | 7/10/2012 | 7/10/2012 2:44:22 PM | P | PASS |
|
|
John - ceiling grid Phone #: ###-####. grid ok for cover.
|
BLD11-02589
| BLD-Final | 7/10/2012 | 7/10/2012 | 7/10/2012 2:28:36 PM | P | FAIL |
|
|
Still needs to remove locking device from rear door and provide panic hardware at main entry door. All other issues hace been resolved. Issued 48 hour notice to have remaining issues repaired.
|
ESC07-00733
| Random Inspection | 7/10/2012 | 7/10/2012 | 7/10/2012 1:58:48 PM | P | PASS |
|
|
|
BLD07-01179
| BLD-Energy code compliance | 7/10/2012 | 7/10/2012 | 7/10/2012 1:58:30 PM | P | PASS |
|
|
Steve Phone #: ###-####
|
ESC12-00484
| Site Preparation | 7/10/2012 | 7/10/2012 | 7/10/2012 1:49:08 PM | P | PART |
|
|
Needs to post ESC permit sign.
|
BLD12-01161
| BLD-Footing | 7/9/2012 | 7/10/2012 | 7/10/2012 1:48:31 PM | P | PASS |
|
|
Hyrum Phone #: ###-####
|
BLD12-01780
| BLD-Footing | 7/9/2012 | 7/10/2012 | 7/10/2012 12:20:15 PM | A | PASS |
|
|
Brad Phone #: ###-####
|
GCB12-00003
| GCB-Framing | 7/9/2012 | 7/10/2012 | 7/10/2012 12:06:42 PM | A | PASS |
|
|
Steve @ ###-####. Framing for new exterior soffit and facia at east side of building per bulliten #2.
|
GCB12-00028
| GCB-Ceiling Grid | 7/9/2012 | 7/10/2012 | 7/10/2012 11:24:08 AM | A | PASS |
|
|
Robert @ ###-####. Hardlids ok to cover.
|
GCB12-00075
| GCB-Footing | 7/9/2012 | 7/10/2012 | 7/10/2012 10:53:36 AM | A | NR |
|
|
Ryan @ ###-####. not ready. Will need to reschedule.
|
ESC12-00705
| Random Inspection | 7/10/2012 | 7/10/2012 | 7/10/2012 10:32:46 AM | A | PASS |
|
|
|
BLD12-01539
| BLD-Other | 7/9/2012 | 7/10/2012 | 7/10/2012 10:32:26 AM | A | PASS |
|
|
Pier for poles -- Barrie Phone #: ###-####
|
BLD12-01512
| BLD-Foundation | 7/9/2012 | 7/10/2012 | 7/10/2012 10:08:32 AM | A | PASS |
|
|
DANE Phone #: ###-####. Bldg 11, perimeter stem walls and column pedestals ok. Also received RFI from engineer noting only 2 #4 horizontals in stemwalls.
|
ESC12-00371
| Site Preparation | 7/10/2012 | 7/10/2012 | 7/10/2012 10:03:12 AM | A | PART |
|
|
Needs to post ESC permit signs at main enterance. Also went over ESC plan with Kelly. Verbal corection notice given to post ESC signs.
|