FIR14-00222
| INSP-Supply line flush | 7/10/2014 | 7/10/2014 | 7/10/2014 3:18:15 PM | P | PASS |
|
|
Inspection was not for a flush but for a cover inspection of the underground supply. The cover inspection passed and the pipe can be buried.
|
FIR14-00358
| INSP-Final Inspection | 7/9/2014 | 7/10/2014 | 7/10/2014 1:59:11 PM | P | PASS |
|
|
permit finaled
|
FIR14-00374
| INSP-Final Inspection | 7/9/2014 | 7/10/2014 | 7/10/2014 1:58:15 PM | P | PASS |
|
|
permit finaled
|
FIR14-00228
| INSP-Sprinkler Rough-in | 7/9/2014 | 7/10/2014 | 7/10/2014 1:22:00 PM | A | PASS |
|
|
See the city approved plans for rooms marked "ok" where piping can be covered.
|
FIR14-00115
| INSP-Sprinkler Rough-in | 7/9/2014 | 7/10/2014 | 7/10/2014 10:16:24 AM | A | PASS |
|
|
See the city approved plans for the sheets marked "ok" where the rough-in has passed. Additional fittings and elevation change needs to be addressed as well as one missing EQ brace. A "Big A**" Ceiling fan is being installed that may be an issue with sprinkler discharge.
|
BLD14-01196
| FIRE-Final Inspection | 7/9/2014 | 7/10/2014 | 7/10/2014 8:06:33 AM | A | PASS |
|
|
Life safety passed
|
BLD14-00251
| FIRE-Final Inspection | 7/9/2014 | 7/10/2014 | 7/10/2014 8:05:37 AM | A | PART |
|
|
Life safety passed for the Radiology Area (Phase I)
|
FIR14-00320
| INSP-Alarm Testing | 7/9/2014 | 7/10/2014 | 7/10/2014 7:57:45 AM | A | DONE |
|
|
Phase I fire alarm complete
|