Inspections for the day of: Friday, July 10, 2015.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorThomas Walsh
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD13-03405 FIRE-Final Inspection7/9/20157/10/20157/10/2015 4:28:30 PMAPART
TCO inspection for Towers 1 and 2, including exit signs, emergency lights, fire extinguishers, etc. for partial occupancy for this portion of the building. Fire sprinklers and fire alarm system testing for this area is completed. A temporary one-hour wall and fire door separates towers &/2 from towers 3&4. Unit EVAC plans are currently being made up and are pending.
OK to occupy Towers 1 & 2 - all floors.
FIR13-00725 INSP-Final Inspection7/8/20157/10/20157/10/2015 4:27:41 PMAPASS
Completion of fire alarm interface for Jump Bldg (above parking garage), including 5th and 6th floor wet pipe waterflows, tampers, etc.
Test of 6 dry-pipe valves supplying standpipes for exit stairs in the above ground parking garage - three located at grade level, and three located in the lower parking garage. All six tested satisfactorily, including low-air alarms and waterflow alarms. All six dry pipe valves were trip tested to ensure proper operation.
NOTE: U/G parking and Helix systems are on a separate permit.
FIR14-00365 INSP-Final Inspection7/10/20157/10/20157/10/2015 4:27:28 PMPPASS
Trip test of the dry-pipe valves for the Helix at levels 2 and 3. All tested OK
FIR13-00167 INSP-Final Inspection7/10/20157/10/20157/10/2015 4:26:56 PMPPASS
Testof the four (4) dry pipe systems protecting the underground parking garage, including fire alarm interface of low-air, waterflow and tampers. and trip tests of the dry-pipe valves. All tested satisfactorily.
NOTE: FDC on 11th street not functional yet. to be hydrotested and flushed.
FIR14-00430 INSP-Final Inspection7/10/20157/10/20157/10/2015 2:52:11 PMPFAIL
Final inspection for the dry pipe valve protecting the north parking garage. Trip test resulted in 85 seconds to water at the IT, so the contractor agreed to install an accelerator. Will retest after this is installed.
FIR14-00531 INSP-Alarm Testing7/9/20157/10/20157/10/2015 2:48:36 PMAPART
Inspection of A/S for Towers 1 # 2 sections of the building - all floors. TCO is requested for this section of the building, so this was a pre-final inspection for the units in this area of the building. A few escutcheon were missing, but were installed before the end of the inspection. Fire sprinklers for this portion of the building are finaled.
FIR15-00096 INSP-Sprinkler Rough-in/Hydro7/8/20157/10/20157/10/2015 2:44:18 PMPPART
5th floor drop lids unit inspection for the east side units, including unit 512, 513, 514, 515, 517, 518, 519, 522 and 521.
OK to cover drop lids in these rooms.
FIR15-00096 INSP-Sprinkler Rough-in7/8/20157/10/20157/10/2015 12:39:59 PMPPART
5th floor corridor insulation (tenting) for the east side. All corridors on the 5th floor are OK to cover.
FIR14-00875 INSP-Alarm Testing7/9/20157/10/20157/10/2015 12:37:35 PMAPART
Tower 2 fire alarm testing, including elevator # 1 recall functions, MP, SDs, unit smoke detection, SFDs, general notification and rooftop HVAC units serving tower 2.
All devices staisfactorily.
GC is requesting TCO of Tower 1 and 2 (all floors). Fire alarm system has been tested and is functonal for these areas.