BLD17-01120
| FIRE-Final Inspection | 7/10/2017 | 7/10/2017 | 7/10/2017 1:45:05 PM | P | PASS |
|
|
No fire sprinkler modifications, fire alarm inspection is complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
|
FIR17-00355
| INSP-Final Inspection | 7/7/2017 | 7/10/2017 | 7/10/2017 1:43:43 PM | P | PASS |
|
|
Final fire alarm inspection passed/complete
|
FIR17-00308
| INSP-Sprinkler Rough-in/Hydro | 7/9/2017 | 7/10/2017 | 7/10/2017 12:59:12 PM | P | PART |
|
|
Hydrostatic test complete for overhead fire sprinkler piping. Rough in inspection for overhead fire sprinkler piping complete, piping between conditioned area's approved for cover, fire sprinkler piping located in attic spaces cannot be covered until insulation/tenting has been installed over the top of the fire sprinkler piping and tenting passed inspection.
|
BLD15-04468
| FIRE-Final Inspection | 7/6/2017 | 7/10/2017 | 7/10/2017 11:32:10 AM | A | PART |
|
|
Life fire safety inspection complete with exception to the communication between fire panels with the link, TCO extension approved for 30 days in regards to life fire safey per conversation with Scott Arellano.
|
BLD16-03440
| FIRE-Final Inspection | 7/6/2017 | 7/10/2017 | 7/10/2017 10:47:32 AM | A | PART |
|
|
James Phone #: ###-#### has punchlist items from life fire safety conference for TCO requested area, remaining items left to address for TCO reuqested area is the card read secure doors in the basment level and mech 30 level link between existing building and new building, these doors are part of the path of egress, door swing is going against the path of travel, door swing needs to be corrected.
|
FIR17-00037
| INSP-Final Inspection | 7/6/2017 | 7/10/2017 | 7/10/2017 9:34:33 AM | A | PASS |
|
|
Final fire sprinkler inspection for area of work passed/complete.
|