BLD18-03486
| BLD-Final | 7/10/2019 | 7/10/2019 | 7/10/2019 3:45:45 PM | P | FAIL |
|
|
Matt Phone #: ###-####//need to seal penetrations in storage rooms//label fire riser room//anchor railings at stairway//will call for re-isnpection//
|
BLD18-02261
| BLD-Final | 7/9/2019 | 7/10/2019 | 7/10/2019 3:27:13 PM | P | FAIL |
|
|
Nick Phone #: ###-####//need fire/life safety sign off//tried to make contact with listed contact person--left message with no response//will need to call for re-inspection//
|
BLD19-00634
| BLD-Final | 7/9/2019 | 7/10/2019 | 7/10/2019 2:47:33 PM | P | FAIL |
|
|
Teddy Phone #: ###-####//needs electrical permit and inspection//informed contact and homeowner//
|
BLD19-01221
| BLD-Footing | 7/10/2019 | 7/10/2019 | 7/10/2019 2:31:27 PM | P | FAIL |
|
|
Terry- wall footing inspection Phone #: ###-####//foundation wall//tie rebar horizontals into existing//add corner bar//pour footing at step down//
|
BLD18-03121
| BLD-Framing/Rough-in | 7/10/2019 | 7/10/2019 | 7/10/2019 2:28:02 PM | P | CANC |
|
|
Matt Phone #: ###-####
|
BLD18-04546
| BLD-Framing/Rough-in | 7/9/2019 | 7/10/2019 | 7/10/2019 1:34:37 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by James Jackson//framing corrections made//
|
BLD19-01804
| BLD-Foundation | 7/9/2019 | 7/10/2019 | 7/10/2019 1:04:58 PM | P | PART |
|
|
Dane Phone #: ###-####//work in progress...//
|
BLD18-03667
| BLD-Framing/Rough-in | 7/9/2019 | 7/10/2019 | 7/10/2019 12:39:04 PM | A | PASS |
|
|
Joe Phone #: ###-####//truss framing and beams installed per plans for modification//engineering was reveiwed//two electrical wires were fire caulked at the penetrations//
|
BLD19-01915
| BLD-Footing | 7/10/2019 | 7/10/2019 | 7/10/2019 11:55:43 AM | P | PASS |
|
|
Stan - concrete coming at 1 Phone #: ###-####//ok per plans//
|
BLD19-02159
| BLD-Framing/Rough-in | 7/9/2019 | 7/10/2019 | 7/10/2019 11:06:57 AM | A | PASS |
|
|
Dean Phone #: ###-####-call for access code//framing ok per plans//fix damaged wall//no plumbing electrical or mechanical//call for final//
|
BLD18-02898
| BLD-Final | 7/9/2019 | 7/10/2019 | 7/10/2019 10:25:31 AM | A | PASS |
|
|
Damian Phone #: ###-####//final complete per plans//all trades signed of final//
|
BLD18-02898
| DOC - Permit Finaled | 7/10/2019 | 7/10/2019 | 7/10/2019 10:25:02 AM | P | PASS |
|
|
|
BLD19-01714
| BLD-Framing/Rough-in | 7/9/2019 | 7/10/2019 | 7/10/2019 9:07:46 AM | A | PART |
|
|
Dale Phone #: ###-####//engineering changes complete for catilever beams//fireblocking installed//steel stud fur out at 4 hour wall complete//electrical rouh complete//do not cover plumbing until inspected//
|
BLD19-01741
| BLD-Final | 7/8/2019 | 7/10/2019 | 7/9/2019 3:46:22 PM | A | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Rob Maes Inspection cancelled from web by: Rob Maes
|