Inspections for the day of: Friday, July 10, 2020.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJames Ady
TitleELE-INSPECTOR
Phone #914-4683
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE20-02330 Final7/10/20207/10/20207/10/2020 1:56:22 PMPPASS
Homeowner should be onsite Phone #: ###-#### Inspection requested via web by Sean Patton Final ok
ELE20-02272 Final7/7/20207/10/20207/10/2020 1:56:01 PMPPASS
I will call at 12 and schedule a time to meet you onsite with approved plans. Phone #: ###-#### Inspection requested via web by Jesse Simpson Final ok
ELE20-02368 Electrical Rough-In7/10/20207/10/20207/10/2020 12:31:38 PMPPASS
Paul. Home is not occupied back door open. Phone #: ###-#### Inspection requested via web by Sean DeLacy Garage recep circuit, Kitchen ok to cover
ELE20-01757 Electrical Rough-In7/9/20207/10/20207/10/2020 11:05:54 AMAPASS
Jeremiah - No one living in the residence currently /*Screened*/ Phone #: ###-#### Back addition of mud room, den, Pantry and down master bed, bath and closet ok to cover
ELE20-01437 Electrical Rough-In7/9/20207/10/20207/10/2020 10:01:59 AMAPASS
video// chadrick Phone #: ###-#### Office and team rooms 103 walls only ok to cover, Restroom hard lids ok to cover
ELE20-02267 Electrical Rough-In7/9/20207/10/20207/10/2020 9:59:56 AMAPASS
Inspect a trench for cover, with pictures.
Installed 3/4, Sch 80 PVC, from the side of the garage, to a shed in the back yard.
Thank you,
Lonnie Phone #: ###-#### Inspection requested via web by Lonnie Sorichta Underground from house to shed ok to cover
ELE20-00556 Electrical Rough-In7/9/20207/10/20207/10/2020 9:08:39 AMAPART
Please call Rafael for inspection of CMM, prep room, and clean room ceilings. Continuation of hot checking in same rooms as time allows. Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo Re-inspect previously covered ceilings in N side offices & Clean room ceiling ok to cover. Prep rooms, Clean room, Wearhouse restroom hot checked and ready for final
ELE20-00225 Electrical Rough-In7/9/20207/10/20207/10/2020 12:00:00 AMPDONE
Need Trench inspected for back fill Phone #: ###-#### Inspection requested via web by robert feller Underground Feeder conduits on back side to Units along federal way. Units 1-4 not ready. Units 5-12 ok to cover