ESC19-01328
| Aging Inspection | 7/10/2020 | 7/10/2020 | 7/10/2020 12:29:45 PM | | CANC |
|
|
|
ESC19-01328
| DOC - Permit Finaled | 7/10/2020 | 7/10/2020 | 7/10/2020 12:29:38 PM | P | PASS |
|
|
|
ESC20-00126
| BMP Violation | 7/9/2020 | 7/10/2020 | 7/10/2020 11:22:08 AM | P | FAIL |
|
|
Washout not cleaned, no DI protection installed. Second follow up scheduled in case they are waiting for products.
|
ESC19-01120
| General Inspection | 7/10/2020 | 7/10/2020 | 7/10/2020 11:20:38 AM | | PART |
|
|
All request completed except for repair or improvement of sediment controls.
|
ESC19-01081
| DOC - Permit Finaled | 7/10/2020 | 7/10/2020 | 7/10/2020 10:42:13 AM | P | PASS |
|
|
|
ESC19-01070
| DOC - Permit Finaled | 7/10/2020 | 7/10/2020 | 7/10/2020 10:41:55 AM | P | PASS |
|
|
|
ESC19-01077
| Aging Inspection | 7/10/2020 | 7/10/2020 | 7/10/2020 10:41:10 AM | | PASS |
|
|
WIP, still needs to be landscaped and materials stored in driveway.
|
ESC19-01038
| Aging Inspection | 7/10/2020 | 7/10/2020 | 7/10/2020 10:40:40 AM | | PASS |
|
|
WIP on framing, no issues around site.
|
ESC19-01036
| Site Final | 7/9/2020 | 7/10/2020 | 7/10/2020 10:40:15 AM | P | NR |
|
|
|
ESC19-01035
| Site Final | 7/9/2020 | 7/10/2020 | 7/10/2020 10:40:02 AM | P | NR |
|
|
|
ESC19-01718
| General Inspection | 7/9/2020 | 7/10/2020 | 7/10/2020 9:39:07 AM | A | PASS |
|
|
Crew stilll doing plumbing trench work. Will begin roads and footings after trench work completed. Water truck on site, spraying site end of each day. No concrete work or washout on site.
|
ESC19-01207
| Aging Inspection | 7/10/2020 | 7/10/2020 | 7/10/2020 8:40:03 AM | | CANC |
|
|
|
ESC19-01207
| DOC - Permit Finaled | 7/10/2020 | 7/10/2020 | 7/10/2020 8:40:00 AM | P | PASS |
|
|
|
ESC15-00853
| General Inspection | 7/10/2020 | 7/10/2020 | 7/10/2020 8:10:35 AM | | PASS |
|
|
WIP on last units
|
ESC19-01286
| Aging Inspection | 7/10/2020 | 7/10/2020 | 7/10/2020 8:10:20 AM | | CANC |
|
|
|
ESC19-01286
| DOC - Permit Finaled | 7/10/2020 | 7/10/2020 | 7/10/2020 8:10:17 AM | P | PASS |
|
|
|
ESC19-00895
| General Inspection | 7/10/2020 | 7/10/2020 | 7/10/2020 8:09:53 AM | | CANC |
|
|
|
ESC19-01248
| General Inspection | 7/10/2020 | 7/10/2020 | 7/10/2020 8:09:34 AM | | PASS |
|
|
WIP on final units
|
ESC19-00189
| General Inspection | 7/10/2020 | 7/10/2020 | 7/10/2020 8:09:05 AM | | PASS |
|
|
WIP on multiple buildings. Teneants are expected to move into a few buildings end of the month. Site is clean, areas are being watered to keep dust down, sweeper comes twice a week.
|
ESC19-00188
| General Inspection | 7/10/2020 | 7/10/2020 | 7/10/2020 8:08:20 AM | | PART |
|
|
WIP on multiple buildings. Teneants are expected to move into a few buildings end of the month. Site is clean, areas are being watered to keep dust down, sweeper comes twice a week.
|
ESC19-00187
| General Inspection | 7/10/2020 | 7/10/2020 | 7/10/2020 8:08:11 AM | | PASS |
|
|
WIP on multiple buildings. Teneants are expected to move into a few buildings end of the month. Site is clean, areas are being watered to keep dust down, sweeper comes twice a week.
|
ESC19-00186
| General Inspection | 7/10/2020 | 7/10/2020 | 7/10/2020 8:08:02 AM | | PASS |
|
|
WIP on multiple buildings. Teneants are expected to move into a few buildings end of the month. Site is clean, areas are being watered to keep dust down, sweeper comes twice a week.
|
ESC19-00185
| General Inspection | 7/10/2020 | 7/10/2020 | 7/10/2020 8:07:53 AM | | PASS |
|
|
WIP on multiple buildings. Teneants are expected to move into a few buildings end of the month. Site is clean, areas are being watered to keep dust down, sweeper comes twice a week.
|