BLD02-00094
| BLD-Framing/Rough-in | 7/10/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | A | PASS |
|
|
DALE ###-####
|
BLD02-01451
| BLD-Foundation | 7/10/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | A | PASS |
|
|
dan ###-####
|
BLD02-01231
| BLD-Final | 7/10/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | A | CANC |
|
|
keith- ###-#### -call 1st before insp . needs fire insp not structural. 7/11/2002 11:48:15 AM
|
BLD02-01316
| BLD-Framing/Rough-in | 7/11/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 07/11/2002 at 06:33:53. Contact: ###-####.Complete prior c/n. 7/11/2002 10:58:57 AM
|
BLD02-01313
| BLD-Framing/Rough-in | 7/11/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/11/2002 at 06:35:11. Contact: ###-####.
|
BLD02-01334
| BLD-Framing/Rough-in | 7/10/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | A | PASS |
|
|
shear nailing -gary- ###-#### re-insp
|
BLD01-03213
| BLD-Final | 7/10/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 07/10/2002 at 12:26:32. Contact: ###-####.c/n posted on window. 7/11/2002 10:37:52 AM
|
BLD01-02017
| BLD-Final | 7/10/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | A | FAIL |
|
|
###-#### clive needs 24 ga etal to reduce clearances at stove, as per umc and national fuel gas codes. 7/11/2002 12:20:44 PM
|
BLD02-01173
| BLD-Foundation | 7/10/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 07/10/2002 at 13:30:35. Contact: PHILIP MORNING ###-#### AFTERNOON ###-####. Contractor on site, footings not per plans. Told them to recall when constructed in accordance with plans. 7/11/2002 4:11:08 PM
|
BLD02-00558
| BLD-Foundation | 7/10/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 07/10/2002 at 07:17:30. Contact: ###-####.poured at time of inspection. 7/11/2002 5:35:06 PM
|
BLD02-01502
| BLD-Final | 7/10/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | P | PASS |
|
|
JERRY ###-#### ok perm oc. 7/11/2002 6:05:44 PM
|
BLD02-00972
| BLD-Framing/Rough-in | 7/10/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | P | PART |
|
|
TERRY ###-####ok to insulate. 7/11/2002 2:39:43 PM
|
BLD02-00559
| BLD-Footing | 7/11/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 07/11/2002 at 08:20:44. Contact: ###-####.
|
BLD02-01572
| BLD-Footing | 7/11/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | P | PART |
|
|
ft insp- cal ###-#### Arived on site waiting for 1/2 the rebar to be delivered, no approved plans on site footing is not per plan, I have made (2) phone calls, got ahold of the engineer and he verbally said footing would be ok at 14" wide with (2) # 4 horizontals in the footing. Un-approved plans at the site, indicate a 20 " wide footing with (4) #4 bars horizontal. Have been on job site approximately 45 min to do a 5 min inspection also note the concrete truck is on site now. I told them there needs to be an approved plan at the job site for the wall inspection or there will be no pour, As is pouring at there own risk. 7/11/2002 5:02:42 PM 7/11/2002 5:12:57 PM
|
BLD02-00752
| BLD-Framing/Rough-in | 7/11/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | P | PART |
|
|
racking -dean -###-####partial on floor pins. 7/11/2002 3:24:37 PM
|
BLD01-02017
| BLD-Final | 7/11/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | P | PASS |
|
|
|