BLD02-01328
| BLD-Footing | 7/11/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | A | CANC |
|
|
Scheduled by a contractor via Hello! on 07/11/2002 at 07:17:57. Contact: ###-####.
|
BLD02-00353
| BLD-Framing/Rough-in | 7/10/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 07/10/2002 at 07:45:28. Contact: ###-####.FINAL NOT FRAMING--C/N--Penetrations need sealed in 1-Hr wall in garage. 7/11/2002 11:12:30 AM
|
MEC02-01056
| Final | 7/10/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/10/2002 at 09:19:50. Contact: ###-####.
|
BLD02-01099
| BLD-Framing/Rough-in | 7/10/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 07/10/2002 at 10:28:19. Contact: ###-####. House is already sided-no shear inspection performed. No approved plans on site. Issued stop work--to remove siding at holdowns and to provide approved plans--call for re-inspection. 7/11/2002 9:11:30 AM
|
BLD02-01153
| BLD-Other | 7/10/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/10/2002 at 13:57:18. Contact: . Shear-Ok to side 7/11/2002 11:55:33 AM
|
BLD02-01115
| BLD-Framing/Rough-in | 7/10/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | A | PART |
|
|
TERRY ###-#### C/N--ok to insulate 7/11/2002 9:37:00 AM
|
BLD02-00673
| BLD-Framing/Rough-in | 7/10/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | A | PASS |
|
|
BEHIND THE FIREPLACE CARDBOARD ARE THE PLANS AND ENGINEERING FOR SAFEKEEPING PLEASE CALL STEVE ###-#### PRIOR Prior c/n items corrected--engineer signed off for the (2) 9" microlam under stairs to bonus room. 7/11/2002 8:53:15 AM
|
BLD02-01620
| BLD-Foundation | 7/10/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 07/10/2002 at 16:48:36. Contact: ###-####. wip 7/11/2002 2:05:11 PM
|
BLD02-01206
| BLD-Framing/Rough-in | 7/11/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | P | PART |
|
|
GARY ###-#### C/N Ok to insulate. 7/11/2002 2:47:18 PM
|
BLD02-01046
| BLD-Framing/Rough-in | 7/11/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | P | PART |
|
|
terry- ###-####--shear nail Eng. received and constructed per eng. on bay from prior c/n--Ok to side. 7/11/2002 4:06:40 PM
|
BLD02-01131
| BLD-Footing | 7/11/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | P | FAIL |
|
|
ft insp chris- ###-#### House was changed from the one approved by P. and Z. Setbacks appear to be a problem with the house on the lot--informed contractor to not pour and re-submit to zoning. 7/11/2002 1:14:59 PM
|
BLD02-00854
| BLD-Framing/Rough-in | 7/11/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | P | PART |
|
|
TERRY ###-#### Shear--ok 7/11/2002 3:34:09 PM
|
BLD02-00723
| BLD-Final | 7/11/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | P | PASS |
|
|
fn occ- jason ###-#### C. of C. #22461 issued. 7/11/2002 4:28:06 PM
|
BLD02-01349
| BLD-Framing/Rough-in | 7/11/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | P | CANC |
|
|
kevin ###-#### fr KEVIN CALLED IN TO CANCEL THIS INSPECTION WILL RE-CALL WHEN READY 7-11-02///DLD
|
BLD02-01205
| BLD-Other | 7/11/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | P | PASS |
|
|
shear--ok to side 7/11/2002 4:41:50 PM
|
BLD02-01356
| BLD-Footing | 7/11/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | P | PASS |
|
|
|
MEC02-01853
| Rough-in | 7/11/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | P | PASS |
|
|
|
MEC02-01853
| Rough-in | 7/11/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | P | CANC |
|
|
Inspection duplication. 7/11/2002 2:26:29 PM
|
BLD02-01349
| BLD-Framing/Rough-in | 7/11/2002 | 7/11/2002 | 7/11/2002 12:00:00 AM | P | PART |
|
|
Ok to insulate pending electrical approval. 7/11/2002 5:01:30 PM
|