Inspections for the day of: Friday, July 11, 2008.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD08-01194 FIRE-Final Inspection7/11/20087/11/20087/11/2008 5:06:18 PMPFAIL
Provide current inspection tag on the fire extinguisher, remove what appears to be a manual locking device from the rear door and remove the thumbturn deadbolt locking assembly from the main exit.
FIR07-00606 INSP-Sprinkler Rough-in7/11/20087/11/20087/11/2008 3:37:07 PMPPART
See the city approved plans for locations where ceilings can be installed and where additional deficiencies have been found such as improperly installed retaining straps, overspaced heads, missing heads, painted heads and heads blocked by the shower pedastals.
FIR08-00214 INSP-Sprinkler Rough-in/Hydro7/11/20087/11/20087/11/2008 3:33:33 PMPPART
The overhead hydro passed but the FDC was not included in the test as required per NFPA13.
FIR07-00902 INSP-Sprinkler Rough-in/Hydro7/10/20087/11/20087/11/2008 11:43:20 AMAPASS
OH Hydro Inspection for the second floor passed.
BLD08-00277 FIRE-Final Inspection7/10/20087/11/20087/11/2008 10:58:00 AMAPASS
fire life safety passed
FIR08-00381 INSP-Sprinkler Rough-in7/10/20087/11/20087/11/2008 10:12:18 AMAPASS
Sprinkler piping is ok to cover.
BLD07-01707 FIRE-Final Inspection7/10/20087/11/20087/11/2008 8:31:54 AMAPASS
fire life safety passed.