FIR11-00152
| INSP-Final Inspection | 7/11/2013 | 7/11/2013 | 7/12/2013 10:19:31 AM | P | PASS |
|
|
Permit finaled
|
FIR13-00037
| INSP-Sprinkler Rough-in | 7/11/2013 | 7/11/2013 | 7/12/2013 10:18:31 AM | P | PASS |
|
|
Cover inspection for remainder of hard lid ceilings on the second floor passed except for the restrooms in the northwest corner
|
FIR12-00717
| INSP-Sprinkler Rough-in/Hydro | 7/10/2013 | 7/11/2013 | 7/11/2013 12:32:57 PM | A | PASS |
|
|
OH hydro for area 2a passed
|
FIR11-00152
| FIR-Aging Inspection | 7/11/2013 | 7/11/2013 | 7/11/2013 8:01:06 AM | | PASS |
|
|
|
BLD13-01138
| FIRE-Conference | 7/10/2013 | 7/11/2013 | 7/10/2013 3:38:48 PM | A | DONE |
|
|
I stopped at the job site and spoke to Christine. I let her know that for the temporary to be official the proper documentation needs to be processed by the permit tech's down town. As far as the racking permit she stated that she is still waiting on Treasure Valley Fire to provide her with a sprinkler system analysis. I left her some competitors phone numbers and I also left jeff with TVFP a voice message. Also upon looking into the warehouse I saw that the racks were being used so I reminded Christine that per our previous agreement the area under them could be used (floor space) but the racks them selves could not. She said that she had misunderstood me. She is going to remove the product.
|