GCB14-00028
| GCB-Framing | 7/11/2014 | 7/11/2014 | 7/14/2014 10:23:25 AM | P | PASS |
|
|
Mike ###-#### framing and insulation ok ok to sheetrock
|
GCB14-00003
| GCB-Final | 7/11/2014 | 7/11/2014 | 7/14/2014 7:58:36 AM | P | DONE |
|
|
Mix-up on inspection type, Dave Hannah able to inspect
|
BLD13-01634
| BLD-Framing/Rough-in | 7/11/2014 | 7/11/2014 | 7/14/2014 7:57:01 AM | P | PART |
|
|
Requesting framing inspection for elevator service floor 5-7. Except the South side. Please contact Rudy Phone #: ###-#### >> Inspection requested via web by Tim Pendleton
|
BLD13-02437
| BLD-Final | 7/11/2014 | 7/11/2014 | 7/14/2014 7:56:34 AM | P | PART |
|
|
|
BLD14-01966
| BLD-Framing/Rough-in | 7/11/2014 | 7/11/2014 | 7/14/2014 7:54:34 AM | P | NR |
|
|
Carl Phone #: ###-####
|
BLD14-01439
| BLD-Energy code compliance | 7/10/2014 | 7/11/2014 | 7/14/2014 7:52:59 AM | P | PART |
|
|
Phone #: ###-#### >> Inspection requested via web by Matthew Evans ok to cover all but the fire place
|
GCB14-00003
| GCB-Final | 7/11/2014 | 7/11/2014 | 7/11/2014 2:18:11 PM | P | PASS |
|
|
|
GCB14-00003
| GCB-Fndatn/slab ins/fld vent | 7/11/2014 | 7/11/2014 | 7/11/2014 2:16:55 PM | P | CANC |
|
|
per Dave Hannah
|
GCB13-00078
| GCB-Fndatn/slab ins/fld vent | 7/10/2014 | 7/11/2014 | 7/11/2014 2:16:41 PM | A | CANC |
|
|
Richard ###-#### please call prior to let him know when inspector might be on site
|
BLD14-01207
| BLD-Energy code compliance | 7/11/2014 | 7/11/2014 | 7/11/2014 1:15:04 PM | P | PASS |
|
|
Don-please call 20 minutes prior Phone #: ###-####
|
BLD13-00557
| BLD-Final | 7/10/2014 | 7/11/2014 | 7/11/2014 12:58:30 PM | P | PASS |
|
|
Clyde-coming in AM to take care of bond Phone #: ###-####
|
BLD13-00557
| DOC - Permit Finaled | 7/11/2014 | 7/11/2014 | 7/11/2014 12:58:14 PM | P | PASS |
|
|
|
BLD14-00234
| BLD-Energy code compliance | 7/11/2014 | 7/11/2014 | 7/11/2014 12:57:44 PM | P | PASS |
|
|
|
BLD14-00234
| BLD-Framing/Rough-in | 7/11/2014 | 7/11/2014 | 7/11/2014 12:57:18 PM | P | PASS |
|
|
Jeremy Phone #: ###-####
|
BLD14-00929
| BLD-Final | 7/11/2014 | 7/11/2014 | 7/11/2014 12:35:03 PM | P | PASS |
|
|
right side of house thru gate // Dave Phone #: ###-####
|
BLD14-00929
| DOC - Permit Finaled | 7/11/2014 | 7/11/2014 | 7/11/2014 12:34:52 PM | P | PASS |
|
|
|
BLD14-00743
| BLD-Conference | 7/11/2014 | 7/11/2014 | 7/11/2014 12:16:15 PM | P | PASS |
|
|
Need inspection to view sheet rocked soffits. So we can cover with siding. Phone #: ###-#### >> Inspection requested via web by Joshua Edwards
|
BLD14-01648
| BLD-Foundation | 7/10/2014 | 7/11/2014 | 7/11/2014 11:26:15 AM | A | PASS |
|
|
Ken-rebar Phone #: ###-####
|
BLD13-02416
| BLD-Final | 7/10/2014 | 7/11/2014 | 7/11/2014 10:24:21 AM | A | NR |
|
|
Kieth-call to meet Phone #: ###-####
|
BLD13-02436
| BLD-Final | 7/10/2014 | 7/11/2014 | 7/11/2014 10:23:55 AM | A | NR |
|
|
Kieth-call to meet Phone #: ###-####
|
BLD13-02437
| BLD-Final | 7/10/2014 | 7/11/2014 | 7/11/2014 10:22:50 AM | A | NR |
|
|
Kieth-call to meet Phone #: ###-####
|
BLD13-02693
| BLD-Final | 7/10/2014 | 7/11/2014 | 7/11/2014 10:19:12 AM | A | PASS |
|
|
Daryl Phone #: ###-####
|
BLD13-01634
| BLD-Framing/Rough-in | 7/10/2014 | 7/11/2014 | 7/11/2014 9:55:49 AM | A | PART |
|
|
Requesting sheathing inspection for West side of elevator service floor 5-7. Please contact Rudy. Phone #: ###-#### >> Inspection requested via web by Tim Pendleton ext framing and sheetig ok
|
BLD13-01634
| BLD-Conference | 7/10/2014 | 7/11/2014 | 7/11/2014 9:54:29 AM | A | PART |
|
|
Requesting framing inspection at North side passenger elevator from 3-7 floor. Please contact Rudy Phone #: ###-#### >> Inspection requested via web by Tim Pendleton ext sheeting ok and framing ok
|
BLD13-01634
| BLD-Wall cover | 7/9/2014 | 7/11/2014 | 7/11/2014 9:53:34 AM | A | PASS |
|
|
Wall cover inspection for 2nd floor Kitchen studio and service core trash and mechanical rooms contact Neal Mays ###-#### Phone #: ###-#### >> Inspection requested via web by Jeremy Richardson
|