Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR16-00204 INSP-Sprinkler Rough-in/Hydro7/11/20167/11/20167/11/2016 4:47:27 PMPPART
Hydrostatic test complete for overhead fire sprinkler piping on levels 2, 3, 5, and 6. Hydrostatic test for other levels to be completed at later date. Flow switch/tamper switches tested for levels 1 thru 9 on stairwell wet pipe valves, all tested satisfactorily.
FIR16-00008 INSP-Sprinkler Rough-in/Hydro7/11/20167/11/20167/11/2016 3:05:06 PMPCANC
Hydrostatic test was completed for level 1 and 2 of the annex building, wrong FIR permit number for hydrostatic test request, this permit is for 2nd level of headquarters building not the annex.. Correct FIR permit number will need to be requested to have hydrostatic test completed.
FIR16-00314 INSP-Sprinkler Rough-in7/11/20167/11/20167/11/2016 3:00:49 PMPPASS
Rough to cover inspection for overhead fire sprinkler piping on level 3 complete, level 3 overhead fire sprinkler piping approved for cover.
BLD16-01501 FIRE-Final Inspection7/11/20167/11/20167/11/2016 2:50:09 PMPCANC
Inspection request cancelled per conversation with Zack
FIR16-00275 INSP-Sprinkler Rough-in/Hydro7/11/20167/11/20167/11/2016 1:15:47 PMPPASS
Hydrostatic test complete for level 6
FIR16-00081 INSP-Final Inspection7/8/20167/11/20167/11/2016 9:43:31 AMAPASS
Previously noted items addressed/repaired, final fire sprinkler inspection passed/complete.
BLD16-01272 FIRE-Final Inspection7/8/20167/11/20167/11/2016 8:24:55 AMAPASS
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in common area's with current inspection tags. Final life fire safety inspection passed/complete.