BLD01-00332
| BLD-Energy code compliance | 7/10/2001 | 7/12/2001 | 7/12/2001 12:00:00 AM | A | PASS |
|
|
scott ###-#### sheet rock crew will keep fireplace open so the fire wall and fire blocking can be inspected also fire blocking for chase backwall of furnace also up stairs fire wall at overbuild this is for all four units 7/13/2001 3:53:16 PM 7/13/2001 4:21:30 PM
|
BLD01-00331
| BLD-Energy code compliance | 7/10/2001 | 7/12/2001 | 7/12/2001 12:00:00 AM | A | PASS |
|
|
scott ###-#### 7/13/2001 3:47:59 PM see note on 3289 patricia 7/13/2001 3:54:56 PM
|
BLD01-01533
| BLD-Foundation | 7/11/2001 | 7/12/2001 | 7/12/2001 12:00:00 AM | A | PASS |
|
|
###-####
|
BLD01-00781
| BLD-Framing/Rough-in | 7/11/2001 | 7/12/2001 | 7/12/2001 12:00:00 AM | A | PASS |
|
|
###-#### roof framing and sheating 7/12/2001 9:45:58 AM
|
BLD01-01562
| BLD-Footing | 7/11/2001 | 7/12/2001 | 7/12/2001 12:00:00 AM | A | PART |
|
|
bruce ###-#### work in progress checked setbacks all ok 7/12/2001 9:23:36 AM
|
BLD01-00043
| BLD-Final | 7/11/2001 | 7/12/2001 | 7/12/2001 12:00:00 AM | A | FAIL |
|
|
chuck ###-#### c/n on site 7/12/2001 10:16:31 AM
|
BLD01-01568
| BLD-Framing/Rough-in | 7/11/2001 | 7/12/2001 | 7/12/2001 12:00:00 AM | A | PASS |
|
|
CHUCK ###-#### SHEAR PANEL ok to cover 7/12/2001 10:29:53 AM
|
BLD01-01539
| BLD-Energy code compliance | 7/12/2001 | 7/12/2001 | 7/12/2001 12:00:00 AM | A | PASS |
|
|
Added by Inspector: 425 On 7/12/2001 9:57:38 AM all c/n items completed ok to cover
|
MIS01-00116
| BLD-Final | 7/12/2001 | 7/12/2001 | 7/12/2001 12:00:00 AM | P | PASS |
|
|
###-#### ok for perm occ 7/12/2001 1:35:41 PM
|
MEC01-02035
| Rough-in | 7/12/2001 | 7/12/2001 | 7/12/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 07/12/2001 at 10:59:24. Contact: ###-####. still need gas piping done 7/12/2001 3:41:27 PM
|
MEC01-01719
| Rough-in | 7/12/2001 | 7/12/2001 | 7/12/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 07/12/2001 at 11:18:21. Contact: ###-####.
|
MEC01-01720
| Rough-in | 7/12/2001 | 7/12/2001 | 7/12/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 07/12/2001 at 11:19:12. Contact: ###-####.
|
MEC01-01721
| Rough-in | 7/12/2001 | 7/12/2001 | 7/12/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 07/12/2001 at 11:20:01. Contact: ###-####.
|
MEC01-01722
| Rough-in | 7/12/2001 | 7/12/2001 | 7/12/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 07/12/2001 at 11:20:41. Contact: ###-####.
|
BLD01-00912
| BLD-Framing/Rough-in | 7/12/2001 | 7/12/2001 | 7/12/2001 12:00:00 AM | P | PASS |
|
|
Added by Inspector: 425 On 7/12/2001 3:47:46 PM framing ok but need truss engineering ok to insulate pluming is done but no sticker on site
|
BLD01-01574
| BLD-Framing/Rough-in | 7/12/2001 | 7/12/2001 | 7/12/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 07/12/2001 at 08:10:26. Contact: ###-####. shear nailing ok to cover ext 7/12/2001 1:55:02 PM
|
MEC01-01935
| Final | 7/12/2001 | 7/12/2001 | 7/12/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 07/12/2001 at 08:33:29. Contact: ###-####.
|
MEC01-02021
| Final | 7/11/2001 | 7/12/2001 | 7/12/2001 12:00:00 AM | P | PASS |
|
|
###-####
|