PLM02-02081
| Sprinkler (Final) | 7/11/2002 | 7/12/2002 | 7/12/2002 12:00:00 AM | A | NR |
|
|
###-#### CHRIS
|
PLM02-02086
| Sprinkler (Final) | 7/12/2002 | 7/12/2002 | 7/12/2002 12:00:00 AM | P | PASS |
|
|
###-####
|
PLM02-02022
| Sprinkler (Final) | 7/12/2002 | 7/12/2002 | 7/12/2002 12:00:00 AM | P | PASS |
|
|
###-#### brandy
|
PLM02-02069
| Sprinkler (Final) | 7/12/2002 | 7/12/2002 | 7/12/2002 12:00:00 AM | P | PASS |
|
|
DAVID ###-####
|
PLM02-00340
| Final | 7/12/2002 | 7/12/2002 | 7/12/2002 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 07/12/2002 at 09:58:49. Contact: ###-####. temp occ for office area grids 2 thru 9, a thru d, install janitor sink and its water heater, turn oon water to all lavs and drinking fountains, breakroom sink incomplete, temp occ ok. 7/12/2002 3:43:17 PM
|
PLM02-02093
| Plumbing Rough-in | 7/12/2002 | 7/12/2002 | 7/12/2002 12:00:00 AM | P | PASS |
|
|
CRAIG ###-#### R/I
|