FIR07-00022
| FIR-Aging Inspection | 7/12/2007 | 7/12/2007 | 7/13/2007 5:36:32 PM | | DONE |
|
|
Under construction, work in progress.
|
BLD07-00917
| FIRE-Conference | 7/12/2007 | 7/12/2007 | 7/13/2007 5:32:58 PM | P | DONE |
|
|
On site visit, discussed repair of existing emergency lighting at the stairways, project schedule, related fire sprinkler and alarm permits.
|
BLD07-00293
| FIRE-Final Inspection | 7/11/2007 | 7/12/2007 | 7/12/2007 2:54:46 PM | A | PART |
|
|
Fire life safety final pending sprinkler permit pump acceptance test, okay for TOC with S. Rogers permission.
|
BLD06-01663
| FIRE-Final Inspection | 7/11/2007 | 7/12/2007 | 7/12/2007 2:51:17 PM | A | PART |
|
|
Temp occupancy approved with S. Rogers permission pending satisfactory pump acceptance testing for the project related fire sprinkler permit to be completed 7/25, also need to add one exit sign at the NE door as indicated on approved plans.
|
FIR07-00203
| INSP-Final Inspection | 7/11/2007 | 7/12/2007 | 7/12/2007 2:47:32 PM | A | PART |
|
|
Required corrections verified for completion, trip testing passed, resubmittals approved, final pending pump acceptance testing per NFPA 20.
|
FIR07-00208
| INSP-Final Inspection | 7/11/2007 | 7/12/2007 | 7/12/2007 2:45:22 PM | A | PASS |
|
|
Final corrections have been made, fire alarm work passed inspection, permit finaled.
|
FIR07-00514
| INSP-Sprinkler Rough-in/Hydro | 7/12/2007 | 7/12/2007 | 7/12/2007 2:42:39 PM | P | PART |
|
|
OH fire sprinkler install is okay for cover at the drop ceilings except where red lined on approved drawings.
|
FIR07-00505
| INSP-Sprinkler Rough-in | 7/11/2007 | 7/12/2007 | 7/12/2007 2:41:22 PM | A | PART |
|
|
FDC pit and drain are approved.
|
FIR07-00571
| INSP-Sprinkler Rough-in | 7/11/2007 | 7/12/2007 | 7/12/2007 2:40:18 PM | A | PART |
|
|
Fire sprinkler modifications per the scope of work are approved for cover at the drop ceilings.
|
BLD07-00824
| FIRE-Final Inspection | 7/11/2007 | 7/12/2007 | 7/12/2007 2:38:15 PM | A | PASS |
|
|
Fire life safety is satisfactory, noted seals at fire doors to be installed when door frame painting is completed, the temporary max. occ. sign is okay until the permanent one arrives, door hardware is approved as discussed.
|
FIR07-00457
| INSP-Final Inspection | 7/11/2007 | 7/12/2007 | 7/12/2007 2:34:46 PM | A | PASS |
|
|
Fire sprinkler permit finaled.
|
FIR07-00557
| INSP-Sprinkler Rough-in | 7/11/2007 | 7/12/2007 | 7/12/2007 2:33:58 PM | A | PART |
|
|
TI fire sprinkler modifications are acceptable, rough-in passed.
|
BLD07-01628
| FIRE-Final Inspection | 7/11/2007 | 7/12/2007 | 7/12/2007 2:33:02 PM | A | PASS |
|
|
Fire life safety inspection passed.
|
FIR07-00285
| INSP-Sprinkler Rough-in | 7/11/2007 | 7/12/2007 | 7/12/2007 2:30:49 PM | A | PART |
|
|
Heads and piping at the 2nd floor stairway and restroom hard lid ceilings appears satisfactory, however no approved plans were made available on site for verification.
|