Inspections for the day of: Tuesday, July 12, 2011.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR10-00583 INSP-Sprinkler Rough-in7/11/20117/12/20117/12/2011 4:48:08 PMPFAIL
Incompleted C/N items.
FIR10-00583 INSP-Supply line flush7/11/20117/12/20117/12/2011 4:46:36 PMPNR
request for flush. Please call Miguel 1 hr before(###-####). Would also like to complete this the same time as our rough-to-cover for the corrections from our last inspection. Phone #: ###-#### >> Inspection requested via web by Trent Bice
BLD11-00969 FIRE-Conference7/12/20117/12/20117/12/2011 4:46:06 PMPDONE
On site conference regarding existing building fire alarm and sprinkler systems and related modifications due to remodel work.
FIR08-00239 INSP-Sprinkler Rough-in7/12/20117/12/20117/12/2011 4:43:34 PMPPART
Ref. dated plan annotations.
FIR11-00235 INSP-Final Inspection7/11/20117/12/20117/12/2011 4:42:57 PMPPASS
Fire sprinkler work passed field inspection. Permit finaled.
FIR11-00137 INSP-Final Inspection7/11/20117/12/20117/12/2011 4:41:52 PMPPASS
Verified revised plans match installation. Fire sprinkler permit finaled.
FIR08-00239 INSP-Sprinkler Rough-in7/11/20117/12/20117/12/2011 4:40:20 PMAPART
Units A2 and D2 4th floor building #2 okayed for cover at the sheetrock soffits. Also noted on plans areas on the 1st floor buildings# 2 and 3 approved for cover including restrooms, breakroom/kitchen, common area- marked with todays date.