ELE17-01337
| Final | 7/11/2018 | 7/12/2018 | 7/12/2018 2:16:23 PM | P | PART |
|
|
Partial final for bar, kitchen, lighting in meeting room, floor boxes. Phone #: ###-#### Inspection requested via web by Clint Tate Bar not ready receptacles on outside of bar show hot and ground reverse. Pool bonding not complete. Pool GFCI protection for pumps not done. Carpet areas still to cover floor receptacles. Upper level lockouts for HVAC units in rooms not complete. Flag pole lights not complete. Items completed- Kitchen panel covers installed complete, Kitchen circuit directory complete, GFCI protection complete for refrigerators in kitchen areas, Motion sensors over ridden in panel locations. TCO for kitchen and meeting room OK
|
ELE18-02489
| Electrical Rough-In | 7/12/2018 | 7/12/2018 | 7/12/2018 1:13:05 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Levels 2, and 3 bathrooms walls and hard lids rough in ok cover
|
ELE17-02862
| Electrical Rough-In | 7/12/2018 | 7/12/2018 | 7/12/2018 12:11:38 PM | A | PASS |
|
|
units 205 , 206 , 207 , 208 , 217 drop ceilings 502 , 503 , 504 , 505 , 506 , 507 , 508 , 509 , 517 , 518 , 519 Call Craig Phone #: ###-#### Inspection requested via web by Tom Betty Informed elevator contractor needs city permit to continue installation. As noted rough in ok cover
|
ELE18-02011
| Electrical Rough-In | 7/11/2018 | 7/12/2018 | 7/12/2018 10:05:40 AM | A | PASS |
|
|
A ceiling grid inspection is needed for Suite 427. Please call Lynn at ###-#### prior to arrival. Thank you! Phone #: ###-#### Inspection requested via web by Lynn Proctor Grid rough in ok cover
|
ELE17-03734
| Electrical Rough-In | 7/11/2018 | 7/12/2018 | 7/12/2018 9:22:32 AM | A | PASS |
|
|
Requesting re-inspection of the panel wall where the plumbing lines have been relocated per the field meeting Phone #: ###-#### Inspection requested via web by Clint Tate Panel wall rough in ok cover
|
ELE18-02126
| Final | 7/11/2018 | 7/12/2018 | 7/12/2018 8:53:35 AM | A | PASS |
|
|
We are requesting another final on this project. the corrections have been made. Thank you! Our contact is Larry ###-#### Phone #: ###-#### Inspection requested via web by Larry Looney Final ok
|