PLM18-02790
| Final | 7/6/2018 | 7/12/2018 | 7/12/2018 2:26:12 PM | P | PASS |
|
|
INSTALLER JAROD ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt
|
MEC18-03139
| Final | 7/6/2018 | 7/12/2018 | 7/12/2018 2:25:53 PM | P | PASS |
|
|
INSTALLER JAROD ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt
|
PLM18-02015
| Final | 7/11/2018 | 7/12/2018 | 7/12/2018 1:37:09 PM | A | PASS |
|
|
Final inspection for gas piping. Phone #: ###-#### Inspection requested via web by Jason Brashears
|
PLM18-02929
| Sprinkler (Final) | 7/12/2018 | 7/12/2018 | 7/12/2018 10:58:11 AM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Chad Uhlorn
|
PLM18-02936
| Water and/or Sewer | 7/11/2018 | 7/12/2018 | 7/12/2018 10:40:50 AM | A | PART |
|
|
ready now Phone #: ###-#### Inspection requested via web by steve bruneel 4" sewer from addition to main tie in test ok.
|
PLM18-02912
| Pressure Test | 7/11/2018 | 7/12/2018 | 7/12/2018 10:21:06 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Mary LaFayette 5# flue 20# gas tests ok
|
PLM18-02871
| Final | 7/12/2018 | 7/12/2018 | 7/12/2018 12:00:00 AM | P | PASS |
|
|
water heater final ok, inspected when onsite for MIS18-00245
|