Inspections for the day of: Friday, July 13, 2007.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorDixie Fellows
TitleMEC-COM/RES INSPECTOR
Phone #794-6208
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC07-01558 Final7/12/20077/13/20077/13/2007 5:25:11 PMAPASS
Phone #: ###-#### Internet Inspection Request from: misty evans
MEC07-02423 Rough-in7/13/20077/13/20077/13/2007 5:24:43 PMPPART
Phone #: ###-#### Internet Inspection Request from: April Sims..r/i ok...gas not done yet??
MEC07-02287 Pressure Test7/12/20077/13/20077/13/2007 5:23:40 PMAFAIL
robert; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang..call for conference
MEC07-01132 Final7/13/20077/13/20077/13/2007 4:04:29 PMAFAIL
Scheduled by a contractor via Hello! on 7/13/2007 at 6:35:53 AM. Contact: ###-####....outside shut-off valve for f/p in living room?
MEC07-00972 Final7/13/20077/13/20077/13/2007 4:02:44 PMPFAIL
Phone #: ###-#### Internet Inspection Request from: Isela Gutierrez...unable to locate secondary drain for attic furnace...combustibles above and at sides of gas coo-top not per manuf
MEC07-01828 Rough-in7/13/20077/13/20077/13/2007 4:01:11 PMPPASS
billy - reinspection - please call 1/2 hr prior to inspection Phone #: ###-####
MEC07-02465 Rough-in7/13/20077/13/20077/13/2007 1:31:13 PMPFAIL
Phone #: ###-#### Internet Inspection Request from: Shelley Baisch...venting not complete...need manuf specs
MEC07-02309 Pressure Test7/13/20077/13/20077/13/2007 1:30:10 PMPPASS
Phone #: ###-#### Internet Inspection Request from: Scott Wickstrom..60lb u/g test to future new bldg ok
MEC07-01851 Final7/12/20077/13/20077/13/2007 12:51:06 PMPPEND
Roy ###-####...will final when other heating contractor is ready
MEC07-00311 Final7/12/20077/13/20077/13/2007 12:42:30 PMAFAIL
###-####...doors locked...called rachael
MEC07-01680 Pressure Test7/13/20077/13/20077/13/2007 12:41:44 PMAPASS
20lb test to fire pit ok
MEC07-01680 Pressure Test7/12/20077/13/20077/13/2007 12:27:18 PMACANC
###-####
MEC07-01245 Final7/12/20077/13/20077/13/2007 12:24:40 PMAPART
Please call Shane before you head over to the jobsite for areas to be inspected. Thank you ###-#### Phone #: ###-#### Internet Inspection Request from: Sonja Hankel...gas, hydronics for 2nd floor ok...the g/c wanted me to sign off on the shell/core. i told him tht permit wasn't called in and i didn't know if ymc's permit was finaled. the boiler on roof is ok for final on plumbing side only..dixie
MEC07-01245 Rough-in7/12/20077/13/20077/13/2007 12:22:06 PMAPASS
Please call Shane before you head over to the jobsite for areas to be inspected. Thank you ###-#### Phone #: ###-#### Internet Inspection Request from: Sonja Hankel
MEC07-02462 Rough-in7/12/20077/13/20077/13/2007 12:21:16 PMANR
Please call Larry with questions ###-#### Phone #: ###-#### Internet Inspection Request from: Sonja Hankel
MEC07-02461 Rough-in7/12/20077/13/20077/13/2007 12:19:41 PMANR
Please call Larry with questions ###-#### Phone #: ###-#### Internet Inspection Request from: Sonja Hankel