Inspections for the day of: Wednesday, July 13, 2011.
Number of inspections: 10
Percentage of inspections complete: 90 %
Percentage of inspections not complete: 10 %
Contact Information
InspectorDaryl DeGrange
TitleELE-INSPECTION SUPV
Phone #794-1379
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC10-00909 Aging Inspection7/7/20117/7/2011   
ELE11-00537 Rough-In Permanent Service7/11/20117/13/20117/13/2011 5:06:25 PMPPASS
joseph-late afternoon please Phone #: ###-#### rough-in p/s o/h rec ok
ELE11-01345 Final7/12/20117/13/20117/13/2011 3:44:35 PMPNR
Should be 100% by 3:00 Phone #: ###-#### >> Inspection requested via web by Matthew White main disconnect not service rated- branch circuit not pulled to light pole
ELE10-02134 Conference7/12/20117/13/20117/13/2011 2:06:03 PMADONE
Outdoor generator clearance requirements. Chris is the contact his no. is ###-####. Phone #: ###-#### >> Inspection requested via web by Shawna Gates
ELE11-01345 Electrical Rough-In7/12/20117/13/20117/13/2011 12:50:31 PMAPASS
Trench and conduit should be complete by 10:30. Phone #: ###-#### >> Inspection requested via web by Matthew White rough-in ok cover trench
GCE11-00076 GCE-Final7/12/20117/13/20117/13/2011 12:30:51 PMAPASS
FinalBench Sewer District @ ###-#### or ###-####Call for access final ok grounding electrodes
ELE11-01214 Final7/12/20117/13/20117/13/2011 10:27:43 AMAPASS
Phone #: ###-#### >> Inspection requested via web by Tim Dunlop final ok
ELE11-01087 Electrical Rough-In7/12/20117/13/20117/13/2011 10:06:43 AMAPASS
MUCHO Phone #: ###-#### rough-in ok floor heat master bath
ELE11-01044 Final7/12/20117/13/20117/13/2011 9:21:12 AMAPASS
>> Inspection requested via web by Terry Scott final ok kitchen-dinning remodel
ELE11-01530 Final7/12/20117/13/20117/13/2011 8:59:46 AMAPASS
Wayne Phone #: ###-#### 15 amp hot tub circuit-ETL listed final ok