Inspections for the day of: Monday, July 13, 2015.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR15-00334 INSP-Alarm Testing7/13/20157/13/20157/14/2015 9:53:38 AMPFAIL
24 hr air test Boise Spectrum - Bldg B
failed. Door was locked to riser room
FIR15-00331 INSP-Alarm Testing7/13/20157/13/20157/14/2015 9:52:08 AMPPASS
24 hr air test Boise Spectrum - Bldg C
started with guage pressure marked.
BLD15-02214 FIRE-Final Inspection7/13/20157/13/20157/13/2015 2:32:34 PMPPASS
Life safety passed
BLD15-01856 FIRE-Conference7/13/20157/13/20157/13/2015 2:14:44 PMPDONE
The general contractor and I went over life safety requirements. I noted that the locking mechanism on the storage room is to meet ADA
FIR15-00323 INSP-Sprinkler Rough-in/Hydro7/10/20157/13/20157/13/2015 2:11:16 PMPFAIL
Failed due to visible loss on all three guages
BLD15-00117 FIRE-Final Inspection7/13/20157/13/20157/13/2015 2:10:01 PMPFAIL
Provide occupant load signs and small documents
FIR15-00258 INSP-Final Inspection7/13/20157/13/20157/13/2015 10:35:01 AMPPART
The only approved items/devices tested/checked today are flow switch, pump running, tamper switchs and the Suite 200 audio/visual devices. Per the installation contractor phase reversal is not an option which will need to be approved by plan review.
BLD15-00476 FIRE-Final Inspection7/13/20157/13/20157/13/2015 10:28:43 AMPPART
A temporary occupancy for fire life safety was given with scott and jennifer's permission until the building fire alarm system has been upgraded through the new upgrade agreement. Life safety including fire alarm is complete for this suite.
FIR15-00321 INSP-Sprinkler Rough-in/Hydro7/10/20157/13/20157/13/2015 10:16:55 AMAPASS
The overhead hydro passed
FIR15-00353 INSP-Sprinkler Rough-in/Hydro7/10/20157/13/20157/13/2015 10:15:18 AMAPASS
The overhead hydro passed
BLD15-02007 FIRE-Final Inspection7/10/20157/13/20157/13/2015 8:05:52 AMAPASS
Life safety passed
FIR15-00478 INSP-Sprinkler Rough-in7/10/20157/13/20157/13/2015 7:53:37 AMAPASS
Rough-in passed. Piping can be covered.