BLD16-01680
| FIRE-Conference | 7/12/2016 | 7/13/2016 | 7/13/2016 2:38:31 PM | P | DONE |
|
|
Fire conference complete.
|
FIR16-00040
| INSP-Sprinkler Rough-in/Hydro | 7/13/2016 | 7/13/2016 | 7/13/2016 2:12:56 PM | P | PART |
|
|
Partial rough to cover inspection complete for underground main supply located on southside of jobsite, partial cover is approved for underground supply running from west to east on southside of project, change of direction where main turns to go into building will be inspected at later date.
|
FIR16-00305
| INSP-Sprinkler Rough-in | 7/13/2016 | 7/13/2016 | 7/13/2016 1:51:53 PM | P | PART |
|
|
Partial rough to cover complete for level 2 overhead fire sprinkler piping, notated the city approved drawings with blue highlighter/red ink, the overhead fire sprinkler piping approved for cover.
|
FIR15-00809
| INSP-Sprinkler Rough-in | 7/12/2016 | 7/13/2016 | 7/13/2016 9:59:16 AM | P | CANC |
|
|
Not ready for rough in inspection for overhead sprinkler piping for level 3, area's on level 3 missing tenting insulation, insulation needs to be completely installed for rough in inspection for cover to be approved.
|
FIR15-00809
| INSP-Sprinkler Rough-in/Hydro | 7/12/2016 | 7/13/2016 | 7/13/2016 9:56:45 AM | P | PASS |
|
|
Hydrostatic test for overhead fire sprinkler piping complete for level 3, overhead fire sprinkler hydrostaic test for this building complete.
|
FIR16-00275
| INSP-Sprinkler Rough-in/Hydro | 7/12/2016 | 7/13/2016 | 7/13/2016 9:19:33 AM | P | DONE |
|
|
Rough to cover inspection for overhead fire sprinklers complete for level 6 as well as overhead fire sprinkler hydrostatic test for level 6.
|
FIR16-00008
| INSP-Sprinkler Rough-in/Hydro | 7/12/2016 | 7/13/2016 | 7/13/2016 9:17:56 AM | P | DONE |
|
|
Notes entered into FIR15-00602 for overhead sprinkler hydrostatic test completed on levels 1 and 2 of annex building.
|
FIR15-00602
| INSP-Sprinkler Rough-in/Hydro | 7/12/2016 | 7/13/2016 | 7/13/2016 9:12:54 AM | P | PASS |
|
|
Hydrostatic test for overhead fire sprinkler piping on levels 1 and 2 complete.
|
BLD14-02800
| FIRE-Final Inspection | 7/11/2016 | 7/13/2016 | 7/13/2016 9:11:38 AM | A | PASS |
|
|
FInal life fire safety inspection passed/complete.
|
BLD15-04479
| FIRE-Final Inspection | 7/12/2016 | 7/13/2016 | 7/13/2016 9:10:46 AM | A | PASS |
|
|
Previously noted issue with fire sprinklers repaired, fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers in common area's with current inspection tags. Final life fire safety inspection passed/complete.
|