Inspections for the day of: Wednesday, July 14, 2010.
Number of inspections: 7
Percentage of inspections complete: 86 %
Percentage of inspections not complete: 14 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR05-00109 INSP-Conference7/2/20107/7/2010 A 
Follow up conference with Mike; ###-####
BLD10-01416 FIRE-Final Inspection7/13/20107/14/20107/14/2010 2:57:39 PMPFAIL
Remove the dead bolt and provide single action hardware on the office door, provide tagged fire extinguisher as discussed and install the missing ceiling tiles.
FIR10-00220 INSP-Sprinkler Rough-in7/14/20107/14/20107/14/2010 2:50:21 PMPPASS
The lobby area sprinkler piping is ok to cover. See the city approved plans for specific area marked with todays date.
FIR10-00032 INSP-Sprinkler Rough-in7/14/20107/14/20107/14/2010 2:48:47 PMPPASS
The sprinkler piping in phase 3B is ok to cover. See the city approved plans marked with todays date for specific area.
FIR03-00082 INSP-Final Inspection7/14/20107/14/20107/14/2010 2:47:50 PMPPASS
Permit finaled. The pendant spacing in the coolers has been corrected.
FIR09-00611 INSP-Final Inspection7/13/20107/14/20107/14/2010 11:05:15 AMAFAIL
Todays inspection was for the revised risers. The new inspectors tests and flow switches functioned correctly. Also inspected were the phase 13 sprinkler piping which can be covered. Sprinkler coverage is lacking in an entry foyer in this same area.
BLD10-01379 FIRE-Final Inspection7/13/20107/14/20107/14/2010 10:39:04 AMAFAIL
A wall has been removed which left several sprinkler pendants located too close to one another which will require a sprinkler permit, provide single action lever hardware on the three doors as discussed, provide tagged fire extinguisher, provide suite number and sticker at the main exit.