FIR11-00272
| INSP-Final Inspection | 7/13/2011 | 7/14/2011 | 7/14/2011 3:24:51 PM | P | FAIL |
|
|
Street, city and state address has not been set up and one smoke detector is located too close to an air grill.
|
FIR11-00080
| INSP-Final Inspection | 7/14/2011 | 7/14/2011 | 7/14/2011 3:21:08 PM | P | FAIL |
|
|
Ok to final when the project related fire alarm permit is finaled.
|
BLD10-02263
| FIRE-Final Inspection | 7/14/2011 | 7/14/2011 | 7/14/2011 3:14:54 PM | P | PASS |
|
|
life safety passed
|
BLD11-01322
| FIRE-Final Inspection | 7/13/2011 | 7/14/2011 | 7/14/2011 3:12:27 PM | A | PASS |
|
|
Life safety passed.
|
FIR11-00167
| INSP-Sprinkler Rough-in/Hydro | 7/13/2011 | 7/14/2011 | 7/14/2011 11:34:01 AM | A | FAIL |
|
|
The hydro test could not be performed due to additional upright heads required around the x-ray room and on the back side of the roof access door. Also the most current set of plans was not on site.
|
BLD11-01186
| FIRE-Final Inspection | 7/13/2011 | 7/14/2011 | 7/14/2011 9:58:35 AM | A | PASS |
|
|
Life safety passed. Taylor Brothers will have the two small fire extinguishers replaced this afternoon per Mary.
|
FIR11-00159
| INSP-Sprinkler Rough-in | 7/13/2011 | 7/14/2011 | 7/14/2011 9:20:12 AM | A | PART |
|
|
Todays inspection was to verify that several of the previous corrections had been addressed on the lower level. They have been marked "ok" in red ink. One pendant still had not been installed in a hard lid and the earthquake bracing for the mains was incorrect.
|