Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD15-01638 FIRE-Final Inspection7/13/20157/14/20157/14/2015 3:08:43 PMACANC
Thanks Matt, Phone #: ###-#### Inspection requested via web by Richard Schultz
BLD15-00487 FIRE-Final Inspection7/14/20157/14/20157/14/2015 2:47:26 PMPFAIL
Life safety will be ok to final when the project related fire alarm and fire sprinkler permits are finaled
FIR15-00481 INSP-Final Inspection7/14/20157/14/20157/14/2015 2:45:31 PMPFAIL
Second flow switch is not activating the outside alarm bell
FIR15-00298 INSP-Final Inspection7/14/20157/14/20157/14/2015 2:32:15 PMPFAIL
Painted head and the outside alarm bell did not function on the second flow switch
FIR15-00488 INSP-Final Inspection7/13/20157/14/20157/14/2015 2:30:41 PMAPASS
Permit finaled
FIR15-00317 INSP-Final Inspection7/14/20157/14/20157/14/2015 2:19:43 PMPPASS
permit finaled
FIR15-00449 INSP-Final Inspection7/14/20157/14/20157/14/2015 2:18:31 PMPPASS
permit finaled
BLD15-00486 FIRE-Final Inspection7/14/20157/14/20157/14/2015 2:18:01 PMPPASS
life safety passed
FIR15-00334 INSP-Alarm Testing7/13/20157/14/20157/14/2015 12:03:43 PMPPART
24 hr air test Boise Spectrum - Bldg B started at 9:00am with pressure marked on guage
FIR15-00331 INSP-Alarm Testing7/13/20157/14/20157/14/2015 12:02:33 PMPPASS
24 hr air test Boise Spectrum - Bldg C passed
FIR15-00411 INSP-Final Inspection7/13/20157/14/20157/14/2015 10:25:58 AMAPASS
Permit finaled
FIR15-00415 INSP-Sprinkler Rough-in/Hydro7/13/20157/14/20157/14/2015 9:16:16 AMAFAIL
The overhead hydro failed due to visible loss on the guage. I also noted that in the northwest corner a wall is going to block coverage of an upright head into the small room just off the corridor.
FIR15-00323 INSP-Sprinkler Rough-in/Hydro7/13/20157/14/20157/14/2015 8:37:25 AMAPASS
Overhead rough-in and tenting passed. Piping can be covered.
FIR15-00361 INSP-Sprinkler Rough-in/Hydro7/13/20157/14/20157/14/2015 8:36:40 AMAPASS
Overhead hydro test passed