FIR14-00792
| INSP-Sprinkler Rough-in | 7/14/2015 | 7/14/2015 | 7/14/2015 1:30:12 PM | P | PART |
|
|
Rough to cover inspection for Bldg H wet pipe system for 3rd floor (2nd floor above grade) for units only - see plans for areas inspected today. OK to cover these areas.
|
FIR14-00815
| INSP-Final Inspection | 7/13/2015 | 7/14/2015 | 7/14/2015 10:21:58 AM | A | PART |
|
|
Called in for final inspection of 2nd floor area 1 portion of the building. Research of permit inspections has not identified any hydrotests of any of the wet systems for the building, or the dry systems in the PG. Primary contractor for this project will be back tomorrow. Will compare notes to confirm what further hydrotests are required. Additionally, final inspection of any sprinkler system cannot be granted until fire alarm interface testing can be performed, including water flows, tampers, etc.
|