Inspections for the day of: Monday, July 15, 2013.
Number of inspections: 13
Percentage of inspections complete: 92 %
Percentage of inspections not complete: 8 %
Contact Information
InspectorJim Sly
TitleBLD-COM/RES INSPECTOR
Phone #794-9465
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC13-00014 General Inspection7/9/20137/9/2013   
BLD12-02258 BLD-Final7/12/20137/15/20137/16/2013 10:16:34 AMAPASS
dave Phone #: ###-####
OK for Perm Occ.
BLD13-01558 BLD-Foundation7/15/20137/15/20137/15/2013 4:18:33 PMPCANC
steve Phone #: ###-####
BLD13-01230 BLD-Foundation7/15/20137/15/20137/15/2013 4:17:19 PMPPASS
Navaro Phone #: ###-####
GCB13-00067 GCB-Final7/12/20137/15/20137/15/2013 4:16:13 PMPPART
Todd ###-####
Called in final.........should have been a framing inspection. Framing inspection Pass.
GCB13-00045 GCB-Framing7/15/20137/15/20137/15/2013 4:13:41 PMPNR
Braydon ###-####
GCB13-00043 GCB-Framing7/15/20137/15/20137/15/2013 4:12:40 PMPNR
Braydon ###-####3
GCB13-00044 GCB-Framing7/15/20137/15/20137/15/2013 4:11:45 PMPNR
Braydon ###-####
MIS13-00203 BLD-Conference7/12/20137/15/20137/15/2013 12:16:30 PMADONE
call for lock box code//Ron Garvin Phone #: ###-####
BLD13-01866 BLD-Conference7/15/20137/15/20137/15/2013 12:15:42 PMAPASS
The roof is ready for final inspection.

Thank you Phone #: ###-#### >> Inspection requested via web by Michael La Pointe
BLD13-01866 DOC - Permit Finaled7/15/20137/15/20137/15/2013 12:15:24 PMPPASS
BLD13-01422 BLD-Footing7/12/20137/15/20137/15/2013 11:55:41 AMAPASS
Mike Phone #: ###-####
GCB13-00018 GCB-Final7/12/20137/15/20137/15/2013 10:29:12 AMAPASS
John ###-####
Unable to determine if all other required agencies have finaled. Structural final only.....OK.