FIR13-00723
| INSP-Sprinkler Rough-in | 7/15/2014 | 7/15/2014 | 7/15/2014 3:09:34 PM | P | PASS |
|
|
The remaining basement ceiling can be installed and select areas, as marked, can be installed on the first floor. Second floor piping can not be covered until plan review gives me the ok on the pipe size changes/hydralic calculations.
|
FIR14-00228
| INSP-Sprinkler Rough-in | 7/15/2014 | 7/15/2014 | 7/15/2014 2:40:11 PM | P | PASS |
|
|
See the city approved plans for locations where piping is ok to cover as marked with todays date.
|
FIR14-00452
| INSP-Final Inspection | 7/15/2014 | 7/15/2014 | 7/15/2014 2:39:27 PM | P | FAIL |
|
|
Provide corrected addressing as per conversation and send signal for verification
|
FIR14-00453
| INSP-Final Inspection | 7/15/2014 | 7/15/2014 | 7/15/2014 2:38:55 PM | P | FAIL |
|
|
Provide the corrected addressing as per discussion and resend signal for verification.
|
FIR13-00713
| INSP-Final Inspection | 7/14/2014 | 7/15/2014 | 7/15/2014 2:38:12 PM | P | FAIL |
|
|
Provide all ot the signs/tags/stickers for the final
|
FIR13-00599
| INSP-Final Inspection | 7/14/2014 | 7/15/2014 | 7/15/2014 2:37:32 PM | P | FAIL |
|
|
Provide all signs/tags/stickers for the final and replace the flow switch.
|
FIR14-00412
| INSP-Sprinkler Rough-in | 7/15/2014 | 7/15/2014 | 7/15/2014 12:06:24 PM | P | PASS |
|
|
See the city approved plans for area on the third floor that is ok for the piping to be covered.
|
FIR14-00386
| INSP-Sprinkler Rough-in/Hydro | 7/14/2014 | 7/15/2014 | 7/15/2014 11:57:18 AM | A | PART |
|
|
Tenting on first floor is ok and piping can be covered. Second floor piping can not be covered due to tenting problems.
|
BLD14-01475
| FIRE-Final Inspection | 7/14/2014 | 7/15/2014 | 7/15/2014 11:56:22 AM | A | PASS |
|
|
life safety passed
|
FIR13-00580
| INSP-Sprinkler Rough-in | 7/14/2014 | 7/15/2014 | 7/15/2014 9:28:30 AM | A | PASS |
|
|
See the city approved plans for area where piping can be covered marked with todays date
|