Inspections for the day of: Wednesday, July 16, 2008.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR07-00606 INSP-Sprinkler Rough-in7/16/20087/16/20087/16/2008 5:30:37 PMPFAIL
Re-inspection for noted defficiencies failed due to non-completion of several items, noted missing coverage at the NE entry vestibule, incorrect head spacing, non-compliant seismic bracing, several field modifications in pipe routing compared to the approved plan set, lacking hangers, etc. Contractor to perform a complete walkthrough of the project regarding necessary adjustments and corrections for code compliance prior to the next scheduled site visit as discussed.
BLD08-00996 FIRE-Final Inspection7/15/20087/16/20087/16/2008 5:20:07 PMPPASS
Fire life safety is satisfactory, two PFE's to be attatched on the wall as discussed.
BLD08-00995 FIRE-Final Inspection7/15/20087/16/20087/16/2008 5:17:33 PMPPASS
Fire life safety passed inspection.
FIR07-00606 INSP-Sprinkler Rough-in/Hydro7/15/20087/16/20087/16/2008 5:02:55 PMPPART
OH hydrostatic test for the admin system passed.
FIR08-00414 INSP-Final Inspection7/15/20087/16/20087/16/2008 4:59:45 PMPPASS
Fire sprinkler permit finaled.
FIR08-00415 INSP-Final Inspection7/15/20087/16/20087/16/2008 4:58:21 PMPPASS
Fire sprinkler permit work okayed for final, one missing escutcheon to be installed today per contractor.
BLD08-00658 FIRE-Final Inspection7/15/20087/16/20087/16/2008 11:28:24 AMAPASS
All items on the correction notice verified for compliance, project related fire alarm and sprinkler work is finished, fire life safety finaled.
FIR08-00406 INSP-Final Inspection7/15/20087/16/20087/16/2008 11:26:47 AMAPASS
Fire alarm system modifications passed field inspection, minor adjustments completed on site, permit finaled.
FIR08-00484 INSP-Final Inspection7/15/20087/16/20087/16/2008 11:24:46 AMAPASS
Fire sprinkler work completed satisfactory, permit scope finaled.
FIR08-00248 FIR-Aging Inspection7/16/20087/16/20087/16/2008 11:23:36 AM DONE
Site visit to confirm construction underway, work in progress.