Inspections for the day of: Wednesday, July 16, 2008.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorClint A Smith
TitleEROSION CONTROL INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC06-00136 Aging Inspection7/16/20087/16/20087/17/2008 4:15:29 PM DEFR
Moved to a site final.
ESC08-00315 Tracking Control7/16/20087/16/20087/16/2008 3:18:47 PMPFAIL
Notice of correction.
1. Clean up all sedimet on both sides of street in the gutterpans and in the street.
1. Figure out access control to the lots. (Construction entrance)
3. Correct the info on the ESC signs.
Will re-inspect on 7/21/08
CAS
ESC06-01387 Tracking Control7/16/20087/16/20087/16/2008 10:47:22 AMPFAIL
Need to clean up all sediment on hard surfaces. Also remove sand bags at D.I. and clean d.i. Will reinspect on 7/22/08
ESC08-00173 General Inspection7/16/20087/16/20087/16/2008 10:16:32 AMAFAIL
Need to re-construct entrance into project area. Also construct a proper concrete washout pit. Spoke with RP over issues. Will re-inspect on 7/24/08
CAS
ESC08-00252 Random Inspection7/16/20087/16/20087/16/2008 9:58:09 AMAPART
site looks good. Rough grading was completed, now they need to maintain the silt fence along the chain link fence. Will re-inspect on 7/18/08
CAS
ESC08-00442 Site Preparation7/16/20087/16/20087/16/2008 9:13:03 AMPNR
Will re-inspect next week.
CAS
ESC08-00411 Site Preparation7/16/20087/16/20087/16/2008 9:07:49 AMPCANC
ESC08-00140 Site Preparation7/9/20087/16/20087/16/2008 8:11:52 AMAPASS
Site looks good. No entrance that are stabilized, due to getting ready to pave. No tracking coming off of project.
CAS