Inspections for the day of: Thursday, July 16, 2009.
Number of inspections: 17
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD09-01050 FIRE-Final Inspection7/16/20097/16/20097/16/2009 4:55:54 PMPPASS
life safety passed.
FIR09-00195 FIR-Aging Inspection7/16/20097/16/20097/16/2009 3:39:54 PM NR
wip
FIR09-00255 INSP-Sprinkler Rough-in/Hydro7/15/20097/16/20097/16/2009 3:38:38 PMAPART
Rough to cover apartment 502 is passed after the pendants in the upstairs apartment were spaced correctly. The problem is the repair work is leaking so the hydro test failed and will need to be rescheduled.
BLD04-01154 FIRE-Final Inspection7/16/20097/16/20097/16/2009 3:35:38 PMPFAIL
Per Jason the exit signs and emergency lights in the basement storage rooms in not required. But the emergency lighting in the stairwell is required. Per Jordan the electricians are having problems with these lights therefore the inspection will need to be rescheduled.
FIR09-00395 INSP-Sprinkler Rough-in7/16/20097/16/20097/16/2009 3:33:40 PMPCANC
Duplicate inspection
FIR09-00419 INSP-Sprinkler Rough-in7/16/20097/16/20097/16/2009 3:33:00 PMPCANC
Rescheduled for tomorrow morning due to time constraints today.
FIR09-00344 INSP-Final Inspection7/16/20097/16/20097/16/2009 12:58:55 PMPPASS
Permit finaled
BLD09-01121 FIRE-Final Inspection7/14/20097/16/20097/16/2009 12:52:25 PMAPASS
Life safety passed. Electrical outlet covers are off due to painting. Notified contact the covers would need to be replaced once painting is complete.
BLD09-00427 FIRE-Final Inspection7/15/20097/16/20097/16/2009 12:26:13 PMAPASS
Fire life safety passed
FIR09-00345 INSP-Final Inspection7/15/20097/16/20097/16/2009 12:25:43 PMAPASS
Permit finaled
FIR09-00033 INSP-Sprinkler Rough-in/Hydro7/10/20097/16/20097/16/2009 11:56:11 AMAPASS
The remainder of system #6 and all of system #9 passed rough-in inspection except for the re-occuring issues with the 4x4 structural beam and the duct/roof penatrations. The racking piping below system #9 was not included in this inspection.
FIR09-00395 INSP-Sprinkler Rough-in7/15/20097/16/20097/16/2009 10:42:47 AMPPASS
Sprinkler piping okay to cover. As-builts required prior to permit final.
FIR09-00347 INSP-Sprinkler Rough-in/Hydro7/15/20097/16/20097/16/2009 10:42:05 AMAPASS
Underground piping okay to cover as marked on plans. This is a partial cover inspection only of the underground.
BLD09-00537 FIRE-Final Inspection7/15/20097/16/20097/16/2009 10:19:07 AMAPART
Fire life safety in areas 'B' and 'D' is passed. These two areas okay to occupy per phase agreement.
FIR09-00316 INSP-Alarm Testing7/15/20097/16/20097/16/2009 10:18:10 AMADONE
Fire alarm system is complete in areas 'B' and 'D'. Un-needed sample tubes from the duct detectors have been removed. However, there are 41 HVAC units with duct detectors but only 39 sample tubes are accounted for. The two missing additional sample tubes will need to be provided prior to final.
BLD09-00449 FIRE-Final Inspection7/15/20097/16/20097/15/2009 12:51:47 PMAPASS
life safety passed
BLD09-00459 FIRE-Final Inspection7/15/20097/16/20097/15/2009 12:17:47 PMAPASS
life safety passed