BLD09-01050
| FIRE-Final Inspection | 7/16/2009 | 7/16/2009 | 7/16/2009 4:55:54 PM | P | PASS |
|
|
life safety passed.
|
FIR09-00195
| FIR-Aging Inspection | 7/16/2009 | 7/16/2009 | 7/16/2009 3:39:54 PM | | NR |
|
|
wip
|
FIR09-00255
| INSP-Sprinkler Rough-in/Hydro | 7/15/2009 | 7/16/2009 | 7/16/2009 3:38:38 PM | A | PART |
|
|
Rough to cover apartment 502 is passed after the pendants in the upstairs apartment were spaced correctly. The problem is the repair work is leaking so the hydro test failed and will need to be rescheduled.
|
BLD04-01154
| FIRE-Final Inspection | 7/16/2009 | 7/16/2009 | 7/16/2009 3:35:38 PM | P | FAIL |
|
|
Per Jason the exit signs and emergency lights in the basement storage rooms in not required. But the emergency lighting in the stairwell is required. Per Jordan the electricians are having problems with these lights therefore the inspection will need to be rescheduled.
|
FIR09-00395
| INSP-Sprinkler Rough-in | 7/16/2009 | 7/16/2009 | 7/16/2009 3:33:40 PM | P | CANC |
|
|
Duplicate inspection
|
FIR09-00419
| INSP-Sprinkler Rough-in | 7/16/2009 | 7/16/2009 | 7/16/2009 3:33:00 PM | P | CANC |
|
|
Rescheduled for tomorrow morning due to time constraints today.
|
FIR09-00344
| INSP-Final Inspection | 7/16/2009 | 7/16/2009 | 7/16/2009 12:58:55 PM | P | PASS |
|
|
Permit finaled
|
BLD09-01121
| FIRE-Final Inspection | 7/14/2009 | 7/16/2009 | 7/16/2009 12:52:25 PM | A | PASS |
|
|
Life safety passed. Electrical outlet covers are off due to painting. Notified contact the covers would need to be replaced once painting is complete.
|
BLD09-00427
| FIRE-Final Inspection | 7/15/2009 | 7/16/2009 | 7/16/2009 12:26:13 PM | A | PASS |
|
|
Fire life safety passed
|
FIR09-00345
| INSP-Final Inspection | 7/15/2009 | 7/16/2009 | 7/16/2009 12:25:43 PM | A | PASS |
|
|
Permit finaled
|
FIR09-00033
| INSP-Sprinkler Rough-in/Hydro | 7/10/2009 | 7/16/2009 | 7/16/2009 11:56:11 AM | A | PASS |
|
|
The remainder of system #6 and all of system #9 passed rough-in inspection except for the re-occuring issues with the 4x4 structural beam and the duct/roof penatrations. The racking piping below system #9 was not included in this inspection.
|
FIR09-00395
| INSP-Sprinkler Rough-in | 7/15/2009 | 7/16/2009 | 7/16/2009 10:42:47 AM | P | PASS |
|
|
Sprinkler piping okay to cover. As-builts required prior to permit final.
|
FIR09-00347
| INSP-Sprinkler Rough-in/Hydro | 7/15/2009 | 7/16/2009 | 7/16/2009 10:42:05 AM | A | PASS |
|
|
Underground piping okay to cover as marked on plans. This is a partial cover inspection only of the underground.
|
BLD09-00537
| FIRE-Final Inspection | 7/15/2009 | 7/16/2009 | 7/16/2009 10:19:07 AM | A | PART |
|
|
Fire life safety in areas 'B' and 'D' is passed. These two areas okay to occupy per phase agreement.
|
FIR09-00316
| INSP-Alarm Testing | 7/15/2009 | 7/16/2009 | 7/16/2009 10:18:10 AM | A | DONE |
|
|
Fire alarm system is complete in areas 'B' and 'D'. Un-needed sample tubes from the duct detectors have been removed. However, there are 41 HVAC units with duct detectors but only 39 sample tubes are accounted for. The two missing additional sample tubes will need to be provided prior to final.
|
BLD09-00449
| FIRE-Final Inspection | 7/15/2009 | 7/16/2009 | 7/15/2009 12:51:47 PM | A | PASS |
|
|
life safety passed
|
BLD09-00459
| FIRE-Final Inspection | 7/15/2009 | 7/16/2009 | 7/15/2009 12:17:47 PM | A | PASS |
|
|
life safety passed
|