BLD13-01432
| FIRE-Final Inspection | 7/16/2013 | 7/16/2013 | 7/16/2013 4:30:31 PM | P | FAIL |
|
|
Need the ceiling tile installed so that I can final the fire sprinkler permit and then final the life safety for this permit.
|
FIR13-00281
| INSP-Final Inspection | 7/16/2013 | 7/16/2013 | 7/16/2013 3:57:15 PM | P | FAIL |
|
|
Ceiling tile not installed yet
|
FIR12-00717
| INSP-Sprinkler Rough-in | 7/16/2013 | 7/16/2013 | 7/16/2013 2:53:45 PM | P | PASS |
|
|
The piping in the exam room restroom is ok to cover.
|
FIR13-00184
| INSP-Sprinkler Rough-in | 7/15/2013 | 7/16/2013 | 7/16/2013 2:36:15 PM | P | PART |
|
|
RTC 2nd floor is mostly ok. Contractor needs to get with plan review but it appears a plan modification is needed since viking pendants were installed instead of tyco. Also the earthquake bracing has not been installed as shown on the plans. I'm ok with the second floor lay-in tile being installed in all locations except where I will need to view earth quake bracing.
|
FIR13-00282
| INSP-Sprinkler Rough-in | 7/15/2013 | 7/16/2013 | 7/16/2013 2:01:40 PM | A | PART |
|
|
Pendant head spacing is ok but insulation is falling from the deck and creating an obstruction to the upright sprinkler heads. Also two runs of sheet rock, which are attached to the trusses above the ceiling are creating an obstruction to the upright sprinkler coverage.
|
FIR13-00271
| INSP-Sprinkler Rough-in | 7/15/2013 | 7/16/2013 | 7/16/2013 9:30:38 AM | A | PASS |
|
|
Ok to cover piping
|