ESC15-00023
| BMP Violation | 7/15/2015 | 7/16/2015 | 7/16/2015 3:06:22 PM | P | PART |
|
|
Wattle installed, most trash collected, permit posted, and DI bag has been emptied out and reinstalled.
Reinspection fee will still hold due to repeat trips. Still some loose sediment on sidewalk and gutter that was not thoroughly cleaned.
No activity, discharges, or new violations. Site is in much better shape but still needs more sweeping to remove transportable dirt.
|
ESC15-00060
| Aging Inspection | 7/16/2015 | 7/16/2015 | 7/16/2015 2:45:56 PM | | PASS |
|
|
Mill District Square close to completion. Interior work and landscaping remain. Will need to clean lot south of access alley. No trackout or discharges. Approved.
|
ESC15-00061
| Aging Inspection | 7/16/2015 | 7/16/2015 | 7/16/2015 2:45:32 PM | | PASS |
|
|
Mill District Square close to completion. Interior work and landscaping remain. Will need to clean lot south of access alley. No trackout or discharges. Approved.
|
ESC14-00588
| General Inspection | 7/16/2015 | 7/16/2015 | 7/16/2015 2:32:33 PM | | PASS |
|
|
Site RP and superindentant is onsite. Entrance area was stabilized with asphalt to prevent track out.
Full site walk through conducted. Site perimeter silt fence and chainlink fencing are in good condition. Lined concrete washout containers are being utilized. No issues at secondary containment area for fueling, no dewatering occuring and no other discharges to Parkcenter or to Logger;s Creek channel of Boise River. No corrections at this time.
|
ESC14-01030
| General Inspection | 7/16/2015 | 7/16/2015 | 7/16/2015 1:45:04 PM | | PASS |
|
|
|
ESC14-01002
| General Inspection | 7/16/2015 | 7/16/2015 | 7/16/2015 1:35:36 PM | | CANC |
|
|
|
ESC14-00944
| General Inspection | 7/16/2015 | 7/16/2015 | 7/16/2015 1:32:13 PM | | CANC |
|
|
|
ESC15-00915
| Site Preparation | 7/16/2015 | 7/16/2015 | 7/16/2015 1:26:16 PM | P | PASS |
|
|
Doug Phone #: ###-####
Perimeter Gatorguard wattle installed and properly staked in and backfilled. ESC permit sign clearly posted. Homeowner RP inspecting site frequenly. Existing driveway will remain and act as stabilized construction entrance.
|
ESC15-00692
| Site Preparation | 7/15/2015 | 7/16/2015 | 7/16/2015 12:17:24 PM | A | PASS |
|
|
Permit sign posted. BMPs for Sunnyridge are installed.
|
ESC14-01044
| General Inspection | 7/16/2015 | 7/16/2015 | 7/16/2015 12:15:59 PM | | CANC |
|
|
|
ESC15-00415
| Site Preparation | 7/15/2015 | 7/16/2015 | 7/16/2015 11:44:24 AM | A | PASS |
|
|
Clint Phone #: ###-####
DH #12 Tahoe project approved for excavation. Permit sign posted, BMPs installed.
|
ESC15-00151
| Aging Inspection | 7/16/2015 | 7/16/2015 | 7/16/2015 9:24:21 AM | | PASS |
|
|
Sidewalk and gutter were cleaned as requested. WIP on backyard retaining wall. No discharges, stockpile of sand/dirt was removed from front yard adjacent to sidewalk. No new corrections.
|
ESC15-00882
| Site Preparation | 7/15/2015 | 7/16/2015 | 7/16/2015 8:56:14 AM | A | PASS |
|
|
8:30 AM requested by Jordan ###-####
Met RP and GC onsite. Work to begin next week. Permit sign posted.
BMPs needed are DI filter bag on corner of Hill & Castle and a perimeter sediment control around the street corner frontage to keep bike lane clean.
Approved.
|
ESC14-00868
| General Inspection | 7/16/2015 | 7/16/2015 | 7/16/2015 8:11:32 AM | | CANC |
|
|
|
ESC15-00076
| General Inspection | 7/16/2015 | 7/16/2015 | 7/16/2015 8:11:12 AM | | CANC |
|
|
|
ESC15-00075
| General Inspection | 7/16/2015 | 7/16/2015 | 7/16/2015 8:10:53 AM | | CANC |
|
|
|
ESC15-00077
| General Inspection | 7/16/2015 | 7/16/2015 | 7/16/2015 8:10:45 AM | | CANC |
|
|
|
ESC15-00089
| Aging Inspection | 7/16/2015 | 7/16/2015 | 7/16/2015 8:10:13 AM | | CANC |
|
|
|
ESC15-00059
| Aging Inspection | 7/16/2015 | 7/16/2015 | 7/16/2015 8:10:02 AM | | CANC |
|
|
|
ESC15-00499
| Complaint Inspection | 7/15/2015 | 7/16/2015 | 7/15/2015 3:48:55 PM | A | PART |
|
|
dust complaint for new del taco work
No fugitive dust at time of inspection, though superintendant stated an operation earlier during the day did creat dust.
I stated for any hauling, grading, and stockpile removal duties dust suppression water applications should be implemented.
|