Inspections for the day of: Tuesday, July 16, 2019.
Number of inspections: 15
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMark Moncarr
TitleELE-INSPECTOR
Phone #685-9023
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE19-02629 Final7/16/20197/16/20197/16/2019 1:18:43 PMPPASS
Please call Brodie with any questions Phone #: ###-#### Inspection requested via web by William Salts Ok final. Changed out 40a 2 pole to a 30 2 pole for new A/C
ELE18-04644 Final7/16/20197/16/20197/16/2019 12:44:17 PMPPASS
Phone #: ###-#### Inspection requested via web by Kevin Perez Ok final.
ELE18-03076 Final7/16/20197/16/20197/16/2019 12:19:10 PMPPASS
Thomas -for the ADU Phone #: ###-#### Ok final.
ELE19-01774 Final7/16/20197/16/20197/16/2019 11:43:52 AMPCANC
Jay Phone #: ###-#### Rescheduled for 7/17/19. Not ready.
ELE18-02006 Final7/16/20197/16/20197/16/2019 11:25:53 AMPPASS
Please contact me 1/2 hour ahead for access. Phone #: ###-#### Inspection requested via web by PAUL PINNEY Ok final. 3/0 blank in closet, and fixture in bath is just out of 3ft zone.
ELE18-01606 Electrical Rough-In7/15/20197/16/20197/16/2019 10:38:58 AMAPASS
B Building
North east 2nd and 3rd Floor Corridor Phone #: ###-#### Inspection requested via web by Stephanie Huston Ok cover 2nd and 3rd floors full N side corridors.
ELE19-01996 Electrical Rough-In7/15/20197/16/20197/16/2019 9:58:13 AMAPASS
Justin Metcalf ###-#### Phone #: ###-#### Inspection requested via web by Samatha Solberg Ok cover up and down levels.
ELE19-02618 Electrical Rough-In7/15/20197/16/20197/16/2019 9:28:39 AMAPASS
Underground inspection for rerouting conduit to new sign location.
Shane is the contact Phone #: ###-#### Inspection requested via web by Deb Ipsen Ok cover conduit on N side of bank for relocation of sign.
ELE17-01330 ELE-Aging Inspection7/16/20197/16/20197/16/2019 9:27:52 AM DONE
Talked to Eric on 7/16. He is going to look into said job.
ELE17-01000 ELE-Aging Inspection7/16/20197/16/20197/16/2019 9:27:21 AM DONE
Talked to contractor on 7/16. Awaiting a few parts to finish house.
ELE19-00515 Final7/15/20197/16/20197/16/2019 9:06:54 AMAPASS
David Phone #: ###-#### Ok final.
ELE19-01745 Final7/15/20197/16/20197/16/2019 9:06:33 AMAPASS
Garage man door in unlocked Phone #: ###-#### Inspection requested via web by Kevin Heideman Ok final.
ELE18-01952 Final7/16/20197/16/20197/16/2019 8:26:36 AMANH
Phone #: ###-#### Inspection requested via web by PAUL PINNEY No access. Talked to electrician, floors were just done last night.
ELE19-02481 Permanent Service7/16/20197/16/20197/16/2019 12:00:00 AMPPASS
ELE19-01992 Final7/15/20197/16/20197/15/2019 2:26:02 PMPPART
Partial final first phase Phone #: ###-#### Inspection requested via web by David Feller Partial final for copier rm, and remodel of conference rm.