Inspections for the day of: Thursday, July 16, 2020.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC20-00066 Site Preparation7/16/20207/16/20207/16/2020 5:21:07 PMPPASS
Dillon - */Screened*/ Phone #: ###-####

Initial BMPs installed including construction entrance, SWPPP signage, and storm drain inlet sediment protection.

Will use ecopan for concrete washout and there is a water truck onsite to control fugitve dust.

Approved.
ESC20-00554 Conference7/16/20207/16/20207/16/2020 5:19:18 PMPDONE
3:30 PM

Showed Cook Bros employee Shaun where to clean up the material, provide a liquid waste receptacle, and pay fine.
ESC20-01043 Site Final7/16/20207/16/20207/16/2020 3:54:38 PMPPASS
Demo complete, site stable and perimeter vegetation and driveway were preseved.
ESC19-00561 Site Final7/16/20207/16/20207/16/2020 3:29:08 PMPPASS
ESC20-00554 BMP Violation7/16/20207/16/20207/16/2020 11:54:00 AMPFAIL
Additional washout and slurry dumped in street. No clean up.
ESC19-00561 Aging Inspection7/16/20207/16/20207/16/2020 11:30:45 AM CANC
rescheduled for site final
ESC19-00790 General Inspection7/16/20207/16/20207/16/2020 11:13:45 AM PASS
WIP. Clean site. Trash contained. Subdivision BMPs installed , including washout pit, storm drain sediment bags, and construction entrances for each site.
ESC19-00867 Aging Inspection7/16/20207/16/20207/16/2020 11:09:10 AM CANC
ESC19-00867 Site Final7/16/20207/16/20207/16/2020 11:09:03 AMPPASS
ESC19-00869 Aging Inspection7/16/20207/16/20207/16/2020 11:08:16 AM CANC
ESC19-00869 Site Final7/16/20207/16/20207/16/2020 11:07:55 AMPPASS