MEC3047451
| INSP - Conference | 7/18/1995 | 7/17/1995 | 7/18/1995 12:00:00 AM | A | PASS |
|
|
meet with rick from quaility heating, to go over gas range and f/p. also he pressurized the gas system for inspection, waited 20 min. test ok 20 minutes
|
MEC3047451
| INSP - Gas pressure test | 7/18/1995 | 7/17/1995 | 7/18/1995 12:00:00 AM | A | PASS |
|
|
gas test ok to gas piping up through floor into cabinet below gas range. f/p was approved before. 50 min.
|
MEC95-00135
| INSP - Framing/ Rough-in | 7/17/1995 | 7/17/1995 | 7/17/1995 12:00:00 AM | | PASS |
|
|
W/H VENT APPROVED FOR R/I 20 MIN
|
MEC95-00213
| INSP - Framing/ Rough-in | 7/17/1995 | 7/17/1995 | 7/17/1995 12:00:00 AM | | FAIL |
|
|
CORRECTIONS ON RA DUCT JOB CONFERENCE WITH HVAC
|
MEC95-00213
| INSP - Gas pressure test | 7/17/1995 | 7/17/1995 | 7/17/1995 12:00:00 AM | | PASS |
|
|
#26164
|
MEC95-00182
| INSP - Gas pressure test | 7/17/1995 | 7/17/1995 | 7/17/1995 12:00:00 AM | A | PASS |
|
|
26156 20 minutes
|
MEC95-00182
| INSP - Framing/ Rough-in | 7/17/1995 | 7/17/1995 | 7/17/1995 12:00:00 AM | A | PASS |
|
|
20 minutes
|
MEC3047673
| INSP - Final | 7/17/1995 | 7/17/1995 | 7/17/1995 12:00:00 AM | A | PASS |
|
|
all corrections were made. 15 minutes
|
MEC3047819
| INSP - Gas log/ Fireplace | 7/17/1995 | 7/17/1995 | 7/17/1995 12:00:00 AM | A | PASS |
|
|
f/ps were framed in add note was posted on f/p about clearances to mantel if built. final 20 minutes
|
MEC95-00023
| INSP - Final | 7/17/1995 | 7/17/1995 | 7/17/1995 12:00:00 AM | A | PASS |
|
|
w/h and furnace change out. w/h and furnace approved. 20 minutes
|
MEC95-00023
| INSP - Gas pressure test | 7/17/1995 | 7/17/1995 | 7/17/1995 12:00:00 AM | A | PASS |
|
|
gas test was witnessed by gas company. 10 minutes
|
MEC3046138
| INSP - Framing/ Rough-in | 7/17/1995 | 7/17/1995 | 7/17/1995 12:00:00 AM | A | PASS |
|
|
mech. shaft lst floor for chapel and one shaft for exhaust duct from basement to roof. both shafts are approved for cover. 35 minutes
|