BLD08-01497
| FIRE-Final Inspection | 7/17/2008 | 7/17/2008 | 7/18/2008 5:44:53 PM | P | PASS |
|
|
Fire life safety finaled.
|
BLD07-03260
| FIRE-Final Inspection | 7/16/2008 | 7/17/2008 | 7/17/2008 5:26:47 PM | P | PASS |
|
|
Fire life safety is satisfactory pending the addition of two exit signs per red lines on the approved plans at the north side of the assembly room, reinspected noted items from the previous visit okay, remainder of fire life safety is satisfactory.
|
BLD07-01248
| FIRE-Final Inspection | 7/16/2008 | 7/17/2008 | 7/17/2008 5:22:19 PM | P | PASS |
|
|
Shell fire life safety inspection completed acceptable.
|
FIR08-00303
| INSP-Final Inspection | 7/17/2008 | 7/17/2008 | 7/17/2008 5:16:30 PM | P | PASS |
|
|
Fire sprinkler permit finaled.
|
FIR07-00902
| INSP-Final Inspection | 7/17/2008 | 7/17/2008 | 7/17/2008 5:13:39 PM | P | PASS |
|
|
Noted correction items are complete, fire sprinkler permit finaled.
|
BLD07-02653
| FIRE-Final Inspection | 7/16/2008 | 7/17/2008 | 7/17/2008 3:54:54 PM | P | NR |
|
|
Final pending repair of non-functional emergency lights.
|
FIR08-00018
| INSP-Sprinkler Rough-in | 7/15/2008 | 7/17/2008 | 7/17/2008 12:40:46 PM | A | FAIL |
|
|
Rough-in inspection for the 6th floor only completed today, see areas annotated on approved plan set for items in need of repair including one missing hanger, one SW to be added due to overspacing, one SW too low, noted several changes in pipe routing due to floor plan modifications which will need to be reflected on a new plan set for accurate documentation of added, relocated or deleted heads.
|
FIR07-00902
| INSP-Supply line flush | 7/16/2008 | 7/17/2008 | 7/17/2008 11:40:09 AM | P | DEFR |
|
|
Duplicate inspection request-flush completed, final inspection scheduled.
|
BLD07-02653
| FIRE-Final Inspection | 7/17/2008 | 7/17/2008 | 7/17/2008 11:37:39 AM | A | FAIL |
|
|
EM lights failed to function at three locations including the open office, womens RR, and east exit discharge. Fire lane marking is complete as required.
|
BLD07-03027
| FIRE-Final Inspection | 7/16/2008 | 7/17/2008 | 7/17/2008 11:34:08 AM | A | NR |
|
|
Need project related fire sprinkler permit finaled previous to final inspection and approval of the building fire life safety.
|
BLD07-03026
| FIRE-Final Inspection | 7/16/2008 | 7/17/2008 | 7/17/2008 11:32:32 AM | A | NR |
|
|
The project related fire sprinkler permit must be requested for final inspection/approval prior to building fire life safety final.
|
FIR05-00806
| INSP-Final Inspection | 7/16/2008 | 7/17/2008 | 7/17/2008 10:36:29 AM | A | PASS |
|
|
Required corrections verified for completion, final field inspection passed, fire sprinkler permit finaled.
|
FIR08-00249
| FIR-Aging Inspection | 7/17/2008 | 7/17/2008 | 7/17/2008 9:52:38 AM | | DONE |
|
|
Site visit confirming construction underway, work in progress.
|