FIR12-00253
| INSP-Sprinkler Rough-in | 7/17/2012 | 7/17/2012 | 7/17/2012 3:52:51 PM | P | PASS |
|
|
Sprinkler piping is ok to cover.
|
FIR12-00294
| INSP-Sprinkler Rough-in | 7/16/2012 | 7/17/2012 | 7/17/2012 3:49:04 PM | P | PASS |
|
|
Todays inspection was for the arm-overs at the roof deck and the drops. An additional inspection will be required for the actual pendant head installation prior to the installation of the ceilings.
|
BLD12-01126
| FIRE-Conference | 7/17/2012 | 7/17/2012 | 7/17/2012 3:45:56 PM | P | DONE |
|
|
I spoke to Trent about getting inspections before the ceiling have been installed.
|
BLD11-01486
| FIRE-Final Inspection | 7/16/2012 | 7/17/2012 | 7/17/2012 12:50:03 PM | A | PASS |
|
|
life safety passed
|
BLD12-01157
| FIRE-Final Inspection | 7/17/2012 | 7/17/2012 | 7/17/2012 12:23:38 PM | P | PASS |
|
|
life safety passed
|