PLM18-03006
| Plumbing Rough-in | 7/17/2018 | 7/17/2018 | 7/17/2018 4:11:54 PM | P | PEND |
|
|
Home is vacant and will be unlocked. Please call Bilk Kirk with any questions. Thanks! 208.880.3988 Phone #: ###-#### Inspection requested via web by Bill Kirk-no building permit pulled bld permit required .....stop work issued and called in for MIS..........plg tested ok.....ds
|
PLM18-02989
| Final | 7/17/2018 | 7/17/2018 | 7/17/2018 3:40:32 PM | P | PASS |
|
|
Please call on way: Darrius ###-#### Phone #: ###-#### Inspection requested via web by Krista Boss
|
PLM17-04080
| Plumbing Rough-in | 7/16/2018 | 7/17/2018 | 7/17/2018 3:18:32 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Kevin Smith water service ok also.........ds
|
PLM18-02990
| Final | 7/17/2018 | 7/17/2018 | 7/17/2018 2:30:43 PM | P | PASS |
|
|
Please cal on way: Josh ###-#### Phone #: ###-#### Inspection requested via web by Krista Boss
|
PLM18-03011
| Groundwork | 7/17/2018 | 7/17/2018 | 7/17/2018 2:19:34 PM | P | PASS |
|
|
will be done at lunch Phone #: ###-#### Inspection requested via web by Semsudin Konjuhovac
|
PLM18-02852
| Plumbing Rough-in | 7/17/2018 | 7/17/2018 | 7/17/2018 2:13:30 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Brian Johansen
|
PLM18-02571
| Groundwork | 7/16/2018 | 7/17/2018 | 7/17/2018 2:00:53 PM | P | PART |
|
|
RILEY IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER marked on plans.......ds
|
PLM18-02946
| Other | 7/16/2018 | 7/17/2018 | 7/17/2018 1:34:28 PM | P | PASS |
|
|
This is an on-site preliminary job walk through, No work has been done yet. We want to be sure the design, install, and inspection process will be accepted by the city before the job begins to avoid problems and delays on this project. Please call me, Scott Ferguson with Master Plumbing, to let me know when you will be onsite so that we can meet you there to go over the job with you. Thank you. ###-####. Phone #: ###-#### Inspection requested via web by Scott Ferguson conference on installing a sand and oil interceptor at tire shop..........ds
|
PLM17-04034
| PLM-Aging Inspection | 7/17/2018 | 7/17/2018 | 7/17/2018 11:29:01 AM | | PASS |
|
|
Spoke with contractor and will check on job status...........
|
PLM18-02463
| Final | 7/16/2018 | 7/17/2018 | 7/17/2018 10:14:05 AM | A | PASS |
|
|
JUSTIN IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER no sign off card on site..........ds
|
PLM18-01679
| Plumbing Rough-in | 7/16/2018 | 7/17/2018 | 7/17/2018 10:11:34 AM | A | PASS |
|
|
please call Josh with any questions Phone #: ###-#### Inspection requested via web by Kelly King
|
PLM18-00472
| Final | 7/16/2018 | 7/17/2018 | 7/17/2018 9:36:12 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige
|
PLM18-03004
| Water and/or Sewer | 7/17/2018 | 7/17/2018 | 7/17/2018 9:18:28 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by matt ford
|
PLM18-03004
| DOC - Permit Finaled | 7/17/2018 | 7/17/2018 | 7/17/2018 9:18:13 AM | P | PASS |
|
|
|
MIS18-00260
| PLM-Conference | 7/16/2018 | 7/17/2018 | 7/17/2018 9:18:02 AM | A | PASS |
|
|
Christina Phone #: ###-#### talked with tenant and a new sewer line and some waste under the bathroom was installed last Nov. Couldnt remember who did the work and driveway is paved over.........ds
|