ELE17-02539
| ELE-Aging Inspection | 7/17/2019 | 7/17/2019 | 7/18/2019 2:14:15 PM | | PASS |
|
|
made contact with Echo...she said will get with Eric Brown and check into getting finaled
|
ELE18-03476
| Final | 7/17/2019 | 7/17/2019 | 7/17/2019 3:21:18 PM | P | PART |
|
|
Zack- interior inspection Phone #: ###-####... interior complete, roof top complete...exterior perimeter of building and oxygen room remaining for complete final
|
ELE18-03476
| Electrical Rough-In | 7/16/2019 | 7/17/2019 | 7/17/2019 3:18:41 PM | P | PASS |
|
|
Zack- inspection Electrical, Dat, and roof Phone #: ###-####....areas stated above inspected for completion
|
ELE19-02085
| Electrical Rough-In | 7/16/2019 | 7/17/2019 | 7/17/2019 3:09:12 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton...wall cover ok...reception hard lid...bathrooms
|
ELE19-02630
| Electrical Rough-In | 7/16/2019 | 7/17/2019 | 7/17/2019 12:56:25 PM | P | PASS |
|
|
Spencer Phone #: ###-####...work location behind baseball field..verified 4" pipe for fiber...18" deep...just for notes to permit...electrical work will be called in at later date for inspection once ready
|
ELE19-02647
| Temporary Service | 7/17/2019 | 7/17/2019 | 7/17/2019 12:31:13 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Robert Murray... t/s u/g new ok
|
ELE19-02393
| Permanent Service | 7/17/2019 | 7/17/2019 | 7/17/2019 12:20:02 PM | P | NR |
|
|
Phone #: ###-#### Inspection requested via web by Buster Bowen...contractor notified
|
ELE19-02554
| Permanent Service | 7/15/2019 | 7/17/2019 | 7/17/2019 10:33:46 AM | A | PASS |
|
|
Please try to come as late in the AM as possible, call Brodie with any questions. Thank You Phone #: ###-#### Inspection requested via web by William Salts... strapping and guide wire on service be done by final so siding and roofing can be done p/s o/h ok...new location on house
|
ELE19-00895
| Electrical Rough-In | 7/16/2019 | 7/17/2019 | 7/17/2019 10:14:31 AM | A | CANC |
|
|
Hard lid ceiling rough in inspection. Brett Jenkins is the contact Phone #: ###-#### Inspection requested via web by Deb Ipsen...ok to cover...3 bathrooms
|
ELE19-02220
| Electrical Rough-In | 7/16/2019 | 7/17/2019 | 7/17/2019 9:29:08 AM | A | PASS |
|
|
Potting and equipotential Owner to be home Phone #: ###-#### Inspection requested via web by Kevin Koomler...potting on light and ground ring...ok
|
ELE18-02523
| Electrical Rough-In | 7/16/2019 | 7/17/2019 | 7/17/2019 9:11:36 AM | A | PASS |
|
|
east lobby ceiling inspection Phone #: ###-#### Inspection requested via web by Debby Pierce... grid ok to cover
|
ELE18-04746
| Electrical Rough-In | 7/16/2019 | 7/17/2019 | 7/17/2019 8:58:23 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton...grid in kitchen/breakroom area...ok to cover
|
ELE19-02308
| Final | 7/17/2019 | 7/17/2019 | 7/17/2019 8:35:15 AM | A | PASS |
|
|
Requesting 8:00 am inspection time. On Site Contact Chris @ ###-#### Phone #: ###-#### Inspection requested via web by Ken Olsen...ok to final
|
ELE19-02308
| Electrical Rough-In | 7/16/2019 | 7/17/2019 | 7/17/2019 8:34:49 AM | A | PASS |
|
|