Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE17-02539 ELE-Aging Inspection7/17/20197/17/20197/18/2019 2:14:15 PM PASS
made contact with Echo...she said will get with Eric Brown and check into getting finaled
ELE18-03476 Final7/17/20197/17/20197/17/2019 3:21:18 PMPPART
Zack- interior inspection Phone #: ###-####... interior complete, roof top complete...exterior perimeter of building and oxygen room remaining for complete final
ELE18-03476 Electrical Rough-In7/16/20197/17/20197/17/2019 3:18:41 PMPPASS
Zack- inspection Electrical, Dat, and roof Phone #: ###-####....areas stated above inspected for completion
ELE19-02085 Electrical Rough-In7/16/20197/17/20197/17/2019 3:09:12 PMPPASS
Phone #: ###-#### Inspection requested via web by Kerri Hamilton...wall cover ok...reception hard lid...bathrooms
ELE19-02630 Electrical Rough-In7/16/20197/17/20197/17/2019 12:56:25 PMPPASS
Spencer Phone #: ###-####...work location behind baseball field..verified 4" pipe for fiber...18" deep...just for notes to permit...electrical work will be called in at later date for inspection once ready
ELE19-02647 Temporary Service7/17/20197/17/20197/17/2019 12:31:13 PMPPASS
Phone #: ###-#### Inspection requested via web by Robert Murray...
t/s u/g new ok
ELE19-02393 Permanent Service7/17/20197/17/20197/17/2019 12:20:02 PMPNR
Phone #: ###-#### Inspection requested via web by Buster Bowen...contractor notified
ELE19-02554 Permanent Service7/15/20197/17/20197/17/2019 10:33:46 AMAPASS
Please try to come as late in the AM as possible, call Brodie with any questions. Thank You Phone #: ###-#### Inspection requested via web by William Salts...
strapping and guide wire on service be done by final so siding and roofing can be done
p/s o/h ok...new location on house
ELE19-00895 Electrical Rough-In7/16/20197/17/20197/17/2019 10:14:31 AMACANC
Hard lid ceiling rough in inspection.
Brett Jenkins is the contact Phone #: ###-#### Inspection requested via web by Deb Ipsen...ok to cover...3 bathrooms
ELE19-02220 Electrical Rough-In7/16/20197/17/20197/17/2019 9:29:08 AMAPASS
Potting and equipotential
Owner to be home Phone #: ###-#### Inspection requested via web by Kevin Koomler...potting on light and ground ring...ok
ELE18-02523 Electrical Rough-In7/16/20197/17/20197/17/2019 9:11:36 AMAPASS
east lobby ceiling inspection Phone #: ###-#### Inspection requested via web by Debby Pierce...
grid ok to cover
ELE18-04746 Electrical Rough-In7/16/20197/17/20197/17/2019 8:58:23 AMAPASS
Phone #: ###-#### Inspection requested via web by Kerri Hamilton...grid in kitchen/breakroom area...ok to cover
ELE19-02308 Final7/17/20197/17/20197/17/2019 8:35:15 AMAPASS
Requesting 8:00 am inspection time. On Site Contact Chris @ ###-#### Phone #: ###-#### Inspection requested via web by Ken Olsen...ok to final
ELE19-02308 Electrical Rough-In7/16/20197/17/20197/17/2019 8:34:49 AMAPASS
Requesting 8:00 am inspection time. On Site Contact Chris @ ###-#### Phone #: ###-#### Inspection requested via web by Ken Olsen...UL listed strip lighting kits installed...using existing circuit...ok