PLM01-02366
| Sprinkler (Final) | 7/17/2001 | 7/18/2001 | 7/18/2001 12:00:00 AM | A | PART |
|
|
Ryan ###-#### tie in ok to cover need to raise P V B up another 5 to 6 inches called contractor 7/18/2001 10:51:26 AM
|
PLM01-02374
| Water and/or Sewer | 7/17/2001 | 7/18/2001 | 7/18/2001 12:00:00 AM | A | PASS |
|
|
###-#### water line only ok to cover 7/18/2001 10:03:26 AM
|
PLM01-02368
| Plumbing Rough-in | 7/17/2001 | 7/18/2001 | 7/18/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/17/2001 at 14:47:04. Contact: ###-####. this is a groundwork only at this time 7/18/2001 11:21:16 AM
|
PLM01-02364
| Water and/or Sewer | 7/17/2001 | 7/18/2001 | 7/18/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by Inspector: 360 On 7/17/2001 3:26:00 PM
|
PLM01-02383
| Water and/or Sewer | 7/18/2001 | 7/18/2001 | 7/18/2001 12:00:00 AM | P | PASS |
|
|
w/s final ###-####
|
PLM01-02387
| Sprinkler (Final) | 7/18/2001 | 7/18/2001 | 7/18/2001 12:00:00 AM | P | PART |
|
|
Bryan ###-#### tie in ok to cover need to install box gravel and test plug's contractor to call when completed 7/18/2001 2:30:40 PM
|
PLM01-02395
| Water and/or Sewer | 7/18/2001 | 7/18/2001 | 7/18/2001 12:00:00 AM | P | PASS |
|
|
###-####
|
PLM01-02214
| Plumbing Rough-in | 7/17/2001 | 7/18/2001 | 7/18/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 07/17/2001 at 07:09:44. Contact: ###-####.
|