MEC95-00062
| INSP - Conference | 7/19/1995 | 7/19/1995 | 10/11/1995 12:00:00 AM | | |
|
|
|
MEC95-00225
| INSP - Framing/ Rough-in | 7/19/1995 | 7/19/1995 | 7/19/1995 12:00:00 AM | | PASS |
|
|
R/I OK CORRECTIONS WERE MADE. 30 MIN
|
MEC95-00225
| INSP - Gas pressure test | 7/19/1995 | 7/19/1995 | 7/19/1995 12:00:00 AM | | PASS |
|
|
GAS LEAK WAS FOUND AND FIXED BY STEVE. NEW GAS TEST PASSED. 26166 20 MIN
|
MEC95-00230
| INSP - Gas pressure test | 7/19/1995 | 7/19/1995 | 7/19/1995 12:00:00 AM | | PASS |
|
|
GAS PIPING OK. 26162. FURN, W/H, F/P. 15 MIN.
|
MEC95-00230
| INSP - Framing/ Rough-in | 7/19/1995 | 7/19/1995 | 7/19/1995 12:00:00 AM | | PASS |
|
|
R/I OK GAS- FURN, W/H, F/P. 20 MIN
|
MEC95-00253
| INSP - Framing/ Rough-in | 7/19/1995 | 7/19/1995 | 7/19/1995 12:00:00 AM | | |
|
|
|
MEC95-00265
| INSP - Gas log/ Fireplace | 7/19/1995 | 7/19/1995 | 7/19/1995 12:00:00 AM | | PASS |
|
|
CHECK COOLING PIPE TERMINATIONS ON FINAL F/P OK
|
MEC95-00238
| INSP - Final | 7/19/1995 | 7/19/1995 | 7/19/1995 12:00:00 AM | P | PASS |
|
|
furnace change out approved. no gas test required. 20 min
|
MEC95-00207
| INSP - Framing/ Rough-in | 7/19/1995 | 7/19/1995 | 7/19/1995 12:00:00 AM | P | FAIL |
|
|
no r/i upper and lower comb.-air need seperated all the way to the source. no literature on under slab heating in basement. f/p still needs outside combustion air 25 min
|
MEC3042472
| INSP - Gas pressure test | 7/19/1995 | 7/19/1995 | 7/19/1995 12:00:00 AM | P | PASS |
|
|
60# test for whole shell. test ok. 45 min. basement-boiler, unit heater. 7th-top floor gas stubbed into each condo., 3/4" line w/shut off.
|
MEC95-00062
| INSP - Final | 7/19/1995 | 7/19/1995 | 7/19/1995 12:00:00 AM | P | PASS |
|
|
access to house final ok. 20 minutes
|