Inspections for the day of: Monday, July 19, 2010.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR04-00349 FIR-Aging Inspection7/19/20107/19/20107/20/2010 8:37:03 AM NR
Jeff stated that it will be scheduled with the last phase of the newer permit.
FIR10-00300 INSP-Sprinkler Rough-in7/19/20107/19/20107/19/2010 3:57:50 PMPPASS
The sprinkler piping in the master bedroom can be covered. I discussed with Richard the requirement for me to verify underground supply piping bury depth and flushing prior to cover.
BLD09-01091 FIRE-Final Inspection7/15/20107/19/20107/19/2010 3:48:46 PMAFAIL
A thumb turn manual dead bolt has been installed on the only exit from the procedure room. This hardware needs to be single action lever type. I was ok with this same hardware on on the secondary exit from the adjoining restroom since the primary exit has approved hardware.
BLD10-00780 FIRE-Final Inspection7/16/20107/19/20107/19/2010 1:05:28 PMAFAIL
There are issues with the project related fire alarm permit. Life safety will be ok to temp when the fire alarm issue has been addressed.
FIR10-00307 INSP-Sprinkler Rough-in/Hydro7/16/20107/19/20107/19/2010 1:01:46 PMAFAIL
The duct smoke detectors and tamper switches tested ok but the facp went into trouble. I left and later returned to the project to see if the issue had been resolved and found that the technicians were still trouble shooting.
FIR10-00258 INSP-Supply line flush7/16/20107/19/20107/19/2010 10:11:37 AMAPASS
The underground flush passed.
FIR10-00256 INSP-Sprinkler Rough-in7/16/20107/19/20107/19/2010 10:10:48 AMAFAIL
I met Mike and Jared on site but there were no city approved plans to perform an inspection with. No inspection was performed.
FIR10-00256 INSP-Supply line flush7/16/20107/19/20107/19/2010 10:09:48 AMAPASS
The underground flush passed.