Inspections for the day of: Tuesday, July 19, 2011.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorBob Reichert
TitleELE-INSPECTOR
Phone #794-1923
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE11-01597 Electrical Rough-In7/19/20117/19/20117/19/2011 1:03:26 PMPPASS
###-#### Office Phone #: ###-#### >> Inspection requested via web by Dan Mitchell ri ok, see final
ELE08-02423 Electrical Rough-In7/19/20117/19/20117/19/2011 1:02:16 PMPPASS
###-#### Office Phone #: ###-#### >> Inspection requested via web by Dan Mitchell ri ok, see final
ELE11-01597 Final7/19/20117/19/20117/19/2011 1:01:46 PMPPASS
###-#### Office Phone #: ###-#### >> Inspection requested via web by Dan Mitchell ok final
ELE11-01313 Permanent Service7/18/20117/19/20117/19/2011 9:57:17 AMAPASS
Please call 30 minutes prior to inspection so Mike can meet you onsite. Mike''s cell number is ###-####. Phone #: ###-#### >> Inspection requested via web by Shawna Gates p/s o/h n ok, will do final later when old service removed and circuits re-fed from new service
ELE10-01493 Final7/18/20117/19/20117/19/2011 9:55:48 AMANR
Please call 30 minutes prior to inspection so Mike can meet you onsite. Mike''s cell number is ###-####. Phone #: ###-#### >> Inspection requested via web by Shawna Gates will do later after painted and plates installed
ELE11-01473 Electrical Rough-In7/19/20117/19/20117/19/2011 8:50:57 AMAPASS
please inspect conduit in the ceiling. The insulators have to wrap all of the paper-backed insulation with a foil and will leave only the j boxes exposed. there are two conduits left undone: 1- for the cooler with wires hanging out 2- is for the hood wiring. Please call with any questions Phone #: ###-#### >> Inspection requested via web by Steve Ruter ok cover ceiling for barrier, will see tile later
ELE11-00557 Electrical Rough-In7/18/20117/19/20117/19/2011 8:06:02 AMAPASS
Underground rough-in inspection - contact is Deeon Martineau ###-#### Phone #: ###-#### >> Inspection requested via web by Scott Campbell looked at u/g for concrete pour, first set of lower conduits, 1st lift