Inspections for the day of: Monday, July 2, 2001.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJoe Tawney
TitleFIRE INSPECTOR
Phone #340-1295
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD00-03443 FIRE-Final Inspection6/29/20017/2/20017/2/2001 12:00:00 AMAPASS
###-#### Reinsp OK for certificate of completion 7/2/2001 11:19:13 AM
BLD01-00207 FIRE-Final Inspection6/29/20017/2/20017/2/2001 12:00:00 AMAFAIL
Final Fail C/N issued 7/2/2001 10:34:13 AM
BLD01-00207 FIRE-Final Inspection6/29/20017/2/20017/2/2001 12:00:00 AMAFAIL
Final Fail C/N issued 7/2/2001 10:34:13 AM
BLD01-00854 FIRE-Final Inspection7/2/20017/2/20017/2/2001 12:00:00 AMACANC
Cancel Should be structural Insp 7/2/2001 8:12:54 AM
BLD01-01225 FIRE-Final Inspection7/2/20017/2/20017/2/2001 12:00:00 AMPPASS
Reinsp OK for permanant occupancy 7/2/2001 4:56:07 PM
BLD01-00525 FIRE-Hydro test above ground7/2/20017/2/20017/2/2001 12:00:00 AMPPASS
###-#### OK on 4th flr hydro test 7/2/2001 1:01:02 PM
BLD00-03043 FIRE-Final Inspection7/2/20017/2/20017/2/2001 12:00:00 AMPFAIL
Final Fail C/N issued 7/2/2001 2:19:00 PM
BLD01-01577 FIRE-Final Inspection7/2/20017/2/20017/2/2001 12:00:00 AMPFAIL
Final fail Provide 6" clearance along walls for 4 X 8 racks 7/2/2001 4:55:39 PM
FIR01-00149 INSP-Sprinkler Rough-in/Hydro7/2/20017/2/20017/2/2001 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 07/02/2001 at 11:26:11. Contact: ###-####.-- -wrong permit #
FIR01-00149 INSP-Sprinkler Rough-in/Hydro7/2/20017/2/20017/2/2001 12:00:00 AMPPART
Spklr rough in Finish EQ bracing of risers, Add 1 head is storage area, Address beam obstruction in storage area 7/2/2001 4:53:44 PM